HomeMy WebLinkAboutPC Meeting 08-18-22 (Reso 2897-2022) - 180 ECR EntitlementsCity of South San Francisco
Resolution No. 2897-2022
P.O. Box 711 (City Hall, 400
Grand Avenue)
South San Francisco, CA
Resolution making findings and recommending that the City Council approve a Use Permit, Design
Review, Tentative Parcel Map and Transportation Demand Management Plan to subdivide the property
to create a total of three parcels, construct one new residential building containing 183 residential units,
three Office/R&D buildings totaling approximately 750,000 square feet, ancillary uses and associated
parking at 180 El Camino Real (Assessor’s Parcel Number 014-183-110) in the El Camino Real Mixed
Use (ECRMX) Zoning District.
WHEREAS, the applicant has proposed to subdivide the property to create a total of three parcels, construct
one new residential building containing 183 residential units, three Office/R&D buildings totaling
approximately 750,000 square feet, ancillary uses and associated parking at 180 El Camino Real (Assessor’s
Parcel Number 014-183-110), (collectively referred to as “Project Site”) in the City; and
WHEREAS, the proposed 180 El Camino Real Residential/R&D Project is located within the El Camino
Mixed-Use (ECRMX) Zoning District; and
WHEREAS, the applicant seeks approval of a Conditional Use Permit (UP21-0013), Design Review (DR21-
0045), Transportation Demand Management Plan (TDM21-0012), and Tentative Parcel Map (PM21-0003), for
the Project; and
WHEREAS, approval of the applicant’s proposal is considered a “project” for purposes of the California
Environmental Quality Act (Public Resources Code §21000, et seq.) (“CEQA”); and
WHEREAS, in 2010 the City Council certified the 2009 Environmental Impact Report (“2009 EIR”) (State
Clearinghouse number 2009062070) in accordance with the provisions of CEQA and the CEQA Guidelines,
which analyzed the potential environmental impacts of the development of the South El Camino area; and
WHEREAS, the City Council also adopted a Statement of Overriding Considerations (“SOC”) in January 2010
in accordance with the provisions of CEQA and the CEQA Guidelines, which carefully considered each
significant and unavoidable impact identified in the EIR and found that the significant environmental impacts
are acceptable considering the project’s economic, legal, social, technological and other benefits; and
WHEREAS, approval of the Applicant’s proposal is considered a “project” for purposes of the California
Environmental Quality Act, Pub. Resources Code § 21000, et seq. (“CEQA”); and
WHEREAS, the 2009 EIR was certified in accordance with the provisions of the California Environmental
File #:22-680,Version:1
City of South San Francisco Page 1 of 9
File #:22-680,Version:1
WHEREAS, the 2009 EIR was certified in accordance with the provisions of the California Environmental
Quality Act (Public Resources Code, §§ 21000, et seq., “CEQA”) and CEQA Guidelines, which analyzed the
potential environmental impacts of the Project; and
WHEREAS, pursuant to CEQA Guidelines Section 15164, an addendum to the 2009 EIR was prepared for the
Project (“2022 Addendum”) which evaluates whether preparation of a Subsequent EIR or Negative Declaration
is required; and
WHEREAS, the 2022 Addendum concludes that in accordance with Public Resources Code § 21166 and
CEQA Guidelines § 15162, the implementation of the 180 ECR Residential/R&D Project will not cause new
significant impacts, will not trigger any new or more severe impacts than were studied in the previously
certified 2009 EIR, that no substantial changes in the project or circumstances justifying major revisions to the
previous EIR have occurred, that no new information of substantial importance has come to light since the 2009
EIR was certified that shows new or more severe significant impacts and there are no new, different or more
feasible mitigation measures to mitigate impacts of the Project that the applicant declines to implement; and
WHEREAS, the City Council previously adopted a Mitigation Monitoring and Reporting Program for the
project and a Statement of Overriding Considerations for the project’s significant and unavoidable impacts,
both of which remain in full force and effect; and
WHEREAS, the Planning Commission held a lawfully noticed public hearing on August 18, 2022 at which
time interested parties had the opportunity to be heard, and to review the Project and supporting documents,
prior to making its recommendation on the Project; and
WHEREAS, the Planning Commission exercised its independent judgment and analysis, and considered all
reports, recommendations and testimony before making a determination on the Project.
NOW THEREFORE, based on the entirety of the record before it, which includes without limitation, the
California Environmental Quality Act, Public Resources Code §21000, et seq. (“CEQA) and the CEQA
Guidelines, 14 California Code of Regulations §15000, et seq.; the South San Francisco General Plan, and
General Plan Environmental Impact Report; the South San Francisco Municipal Code; the 2009 South El
Camino General Plan Amendment EIR and Statement of Overriding Considerations; 2022 Addendum to the
2009 EIR; the Project applications; the 180 El Camino Real Residential/R&D Project Plans, as prepared by
SOM, dated August 10, 2022; all site plans, and all reports, minutes, and public testimony submitted as part of
the Planning Commission’s duly noticed August 18, 2022 meeting; and any other evidence (within the meaning
of Public Resources Code §21080(e) and §21082.2), the Planning Commission of the City of South San
Francisco hereby finds as follows:
SECTION 1 FINDINGS
City of South San Francisco Page 2 of 9
File #:22-680,Version:1
A. General
1. The foregoing recitals are true and correct and made a part of this Resolution.
2. The Exhibits attached to this Resolution, including the 180 ECR Residential/R&D Draft Conditions of
Approval (Exhibit A), Entitlement Plan Set (Exhibit B), Zoning Conformance Checklist (Exhibit C),
and the Transportation Demand Management Program (Exhibit D) are each incorporated by reference
and made a part of this Resolution, as if set forth fully herein.
3. The documents and other materials constituting the record for these proceedings are located at the
Planning Division for the City of South San Francisco, 315 Maple Avenue, South San Francisco, CA
94080, and in the custody of the Planning Manager.
B. Conditional Use Permit
1. The proposed Project is consistent with the standards and requirements of the City’s Zoning Ordinance
and with the provisions of the El Camino Real Mixed Use (ECRMX) Zone District. The Project meets
or exceeds all the general development standards of the El Camino Real Mixed Use Zone District, with
the exception of the building length and separation requirement and hours of operation. The stated
exceptions are permissible and warranted by the City’s Zoning Ordinance, specifically South San
Francisco Municipal Code Sections 20.090.004 and 20.090.006.
2. The proposed Project is consistent with the General Plan and South El Camino Real Planning Subarea
by creating a high-density mixed-use project that includes residential, commercial and employment uses
and emphasizes ground-floor activation, pedestrian and bicycle improvements, connections to transit,
that implements the goals of the General Plan for the South El Camino area, provides a well-articulated
and visually engaging development that implements the goals of the Grand Boulevard Initiative and the
El Camino Real Master Plan and locates parking in a way that is not visually dominant, and is
consistent with the City’s Design Guidelines as they relate to building design, form and articulation.
3. The proposed mixed-use project will not be adverse to the public health, safety, or general welfare of
the community, nor detrimental to surrounding properties or improvements, because the proposed use is
consistent with the approved uses in the General Plan and Zoning Ordinance. The Project proposes high
-density mixed-uses located in the City’s South El Camino area, which is intended for this type of use,
and would be redeveloping underutilized parcels that are proximate to transit, retail, and service uses.
The General Plan has analyzed this type of use and concluded that such mixed uses are not adverse to
the public health, safety, or welfare. As the proposed Project is consistent with other mixed-use and
residential land uses in the El Camino Real Mixed Use District, approval of the Project will not be
detrimental to nearby properties. Further, the proposed use is well- suited to the site, and would improve
the property for surrounding users and the City. In addition, the 2022 Addendum prepared for the
Project concludes that as a result of the Project no new significant or substantially more severe impacts
would result from the Project beyond those previously analyzed and addressed in the 2009 EIR. Further,
the Project has been designed to mitigate external noise, such that the Project’s proximity to the San
Francisco International Airport will not result in adverse impacts to public health, safety or general
City of South San Francisco Page 3 of 9
File #:22-680,Version:1
Francisco International Airport will not result in adverse impacts to public health, safety or general
welfare.
4. The proposed Project complies with applicable standards and requirements of the City’s Zoning
Ordinance, with the exception of the building depth and separation requirement, the parking
requirements and hours of operation. The stated exceptions are permissible and warranted by the City’s
Zoning Ordinance. The proposed Project is located in the El Camino Real Mixed Use District and,
subject to the exceptions discussed above in Section B.1, which are permissible and warranted by the
City’s Zoning Ordinance, meets the minimum standards and requirements for that district.
The exception for the number of parking spaces is allowable under the City’s Municipal Code Section
20.330.006(D), and warranted based on the following findings:
a. Special conditions exist because the site is proximate to both the San Bruno BART station and to
several SamTrans bus lines, including rapid bus service on El Camino Real, and is adjacent to
several large residential neighborhoods and large commercial centers containing retail, restaurants
and services.
b. The proposed parking standard will be adequate for the proposed use because of the offered
alternative solutions for providing and managing parking. The Project is required to implement a
TDM Program on an on-going basis over the life of the Project with a required alternative mode
shift of 40%. The TDM requirements applicable to the Project, the fact that similar reduced
standards have been accepted and/or successfully applied within several large developments in the
City, including both commercial and biotech campuses, and the studies from the Institute of
Transportation Engineers (ITE), all support a reduced parking standard. The project will be
providing parking in keeping with the proposed parking requirements in the pending General Plan
Update and associated Zoning Code, which is establishing parking standards that serve to support
and promote the TDM program.
c. The reduced parking rate reinforces the overall efforts of the City’s General Plan and the TDM
Ordinance, which encourage reduced parking standards as an effective tool in encouraging use of
alternative modes of transportation other than single occupancy vehicles.
d. The parking demand generated by the project will not exceed the capacity of or have a
detrimental impact on the supply of on-street parking in the surrounding area as no on-street parking
is permitted on any of the immediately adjacent streets, including El Camino, South Spruce Ave and
Huntington Ave. As described above, there is ample evidence to support the proposed parking
reduction, and there is added concern that an overabundance of parking could have a deleterious
City of South San Francisco Page 4 of 9
File #:22-680,Version:1
effect on the goals and objectives of the City’s TDM efforts since such would serve as a disincentive
to use of alternative modes of transportation.
5. The exception for the operations occurring on-site between 12:00 A.M. and 6:00 A.M. is allowable
under the City’s Municipal Code Section 20.490.002(B). Operations during these hours will only
include employee access to the research and development uses on a 24-hour basis; public access to the
research and development uses and to the ancillary commercial tenant spaces is not included. The site is
situated directly adjacent to El Camino Real and South Spruce Ave., larger arterial roadways that
provide direct access and that serve as a buffer between the proposed use and residential neighborhoods
in the area. Surrounding residential uses would not be negatively impacted by the limited amount of
research and development tenant use occurring during these hours.
6. The design, location, size, and operating characteristics of the proposed Project are compatible with the
existing and reasonably foreseeable future land uses in the vicinity because the Project proposes mixed-
use development, including residential, commercial and employment uses, in the El Camino Real Mixed
Use District, which is specifically intended for such uses. Further, the Project has been designed to
mitigate external noise, such that the Project will be compatible with the existing and reasonably
foreseeable land uses in the vicinity, including those uses associated with the San Francisco
International Airport.
7. With the exception of the building dimension requirement and parking reduction, the proposed Project
complies with any design or development standards applicable to the zoning district and the use in
question and has been vetted and recommended for approval by the City’s Design Review Board at its
meetings of March 28, 2022 and May 17, 2022.
8. Per South San Francisco Municipal Code Section 20.090.004(A), El Camino Mixed-Use Development
Standards, an increase in FAR and height may be achieved in the ECRMX District through a
combination of the following elements per an incentives program: Transportation Demand
Management (TDM) measures, and provision of off-site improvements, which may include off-site
amenities and or / infrastructure other than standard requirements and improvements. The 180 ECR
Residential/R&D project is consistent with the accepted list of public benefits outlined in South San
Francisco Municipal Code Section 20.090.004(A) has provided a robust TDM program with a 40
percent alternative mode split, intended to reduce peak-hour vehicle trips, and will provide a community
benefits package that includes the expediting of construction of the Safeway project on an adjacent
parcel, median improvements to El Camino Real between South Spruce Avenue and Country Club
Drive, and funds that will help facilitate the construction of a new fire station for the civic center
campus area.Thus, the project is meeting the requirements for the requested FAR and height per the
incentives program.
9. Per South San Francisco Municipal Code Section 20.090.006 (A), ECRMX Supplemental Regulations,
Building Length and Separation, the maximum dimension of the portion of a building above 45’ from
finished grade shall not exceed 125’, and must be separated from another building by 30’. Exceptions
City of South San Francisco Page 5 of 9
File #:22-680,Version:1
finished grade shall not exceed 125’, and must be separated from another building by 30’. Exceptions
and modifications to this requirement may be granted, based on a finding that adequate design features
have been incorporated to create visual variety and avoid a large-scale, bulky, or monolithic appearance.
Building 1 is proposed with a building length of 266’ facing El Camino Real. The building façade has
been designed to have multiple stepbacks, transparency throughout the building, open space terraces on
the third-floor level, and multiple building openings to prevent a monolithic and bulky appearance.
Thus, this is an appropriate exception to the required building length for Building 1.
10. The site is physically suitable for the type of development and density proposed, as the residential,
commercial and employments uses will all benefit from being located in close proximity to the San
Bruno BART station, SamTrans bus routes, surrounding residential, retail and services uses, and
pedestrian and bicycle amenities, and the size and development is appropriate for the location and meets
the City’s land use and zoning standards, as amended by the Conditional Use Permit process. Access to
the site via existing roadways is sufficient as the project is within a built-out urban environment, utilities
are provided on-site or proposed for minor upgrades, and no physical constraints such as topography or
lack of facilities exists that would prevent suitable development.
11. The Planning Commission, pursuant to CEQA Guidelines section 15164, subsection (d), has considered
the 2022 Addendum prepared for the Project including the related environmental analysis, along with
the previously certified 2009 EIR. Upon consideration of the 2022 Addendum, the Planning
Commission finds that the proposed Project will not result in any of the conditions identified in CEQA
Guidelines section 15162 that would require further environmental review through preparation of a
subsequent or supplemental EIR. The Project will not create any new significant impacts or
substantially more severe impacts as compared to those already identified and analyzed in the 2009 EIR.
Further, the Planning Commission finds that there is no new information of substantial importance that
demonstrates new or substantially more severe significant effects, as compared to those identified in the
prior CEQA documents. In addition, there are no new, additional, or more feasible mitigation measures
required to mitigate any impacts of the Project that the applicant declines to implement.
C. Design Review
1. The Project, including Design Review, is consistent with Title 20 of the South San Francisco Municipal
Code because the Project has been designed as a high-density mixed-use project which will provide a
pedestrian-friendly, transit-oriented environment with sustainability elements incorporated.
2. The Project, including Design Review, is consistent with the General Plan because the proposed high-
density mixed-use development is consistent with the policies and design direction provided in the
South San Francisco General Plan for the El Camino Real Mixed Use land use designation by
developing new residential, commercial and employment uses within close proximity to the BART
Station, by activating the streetscapes on El Camino Real and South Spruce Avenue, and by providing
active uses.
3. The Project, including Design Review, is consistent with the applicable design guidelines adopted by
the City Council in that the proposed Project is consistent with the El Camino Real Mixed Use Design
City of South San Francisco Page 6 of 9
File #:22-680,Version:1
the City Council in that the proposed Project is consistent with the El Camino Real Mixed Use Design
Guidelines, as evaluated in the Zoning Ordinance Compliance analysis for the Project.
4. The Project is consistent with the Use Permit for the reasons stated in Section B above.
5. The Project is consistent with the applicable design review criteria in South San Francisco Municipal
Code Section 20.480.006 (“Design Review Criteria”) because the project has been evaluated by the
Design Review Board on March 28, 2022 and May 17, 2022 and found to be consistent with each of the
eight design review criteria included in the Design Review Criteria” section of the Ordinance.
D. Transportation Demand Management Program
1. The Project’s proposed trip reduction measures are feasible and appropriate for the Project, considering
the proposed use or mix of uses and the Project’s location proximate to the San Bruno BART station and
multiple SamTrans bus lines, and adjacency to residential and retail/service uses that will encourage
alternative transportation modes and reduce single occupant vehicle use; and
2. The proposed performance guarantees will ensure that the target 40% alternative mode use established
for the Project will be achieved and maintained. Conditions of approval have been included to require
that the Final TDM Plan, which must be submitted for review and approval prior to issuance of a
building permit, shall outline the required process for on-going monitoring including annual surveys.
E. Tentative Parcel Map
1. The proposed vesting tentative parcel map, prepared by Ware Malcomb and dated August 10, 2022,
including the proposed designs and improvements, is consistent with the City’s General Plan and South
El Camino Real Sub-Area because the tentative map would facilitate the development of a pedestrian-
oriented mixed-use project which would implement the goals of the South El Camino Real Sub-Area.
2. The proposed vesting tentative parcel map is consistent with the standards and requirements of the
City’s Zoning Ordinance.
3. The vesting tentative parcel map complies and meets all the requirements of Title 19 of the South San
Francisco Municipal Code (“Subdivisions”) and with the requirements of the State Subdivision Map
Act, including as to design, drainage, utilities, road improvements, and any offers of dedication.
4. The Project site is physically suitable for the type of development and density proposed, as the mixed-
use project will be located on underutilized parcels on El Camino Real which calls for pedestrian-
oriented high intensity active use along El Camino Real.
5. The vesting tentative parcel map is consistent with the analysis included in the Addendum to the 2009
EIR, and the approval of this vesting tentative map would not result in any new significant
environmental effects or a substantial increase in the severity of any previously identified effects
beyond those disclosed and analyzed in the 2009 EIR adopted by City Council, nor does the vesting
tentative parcel map constitute a change in the Project or change in circumstances that would require
City of South San Francisco Page 7 of 9
File #:22-680,Version:1
tentative parcel map constitute a change in the Project or change in circumstances that would require
additional environmental review.
6. The design and improvements of the vesting tentative parcel map are not in conflict with any existing
public easements.
7. The property is located in a developed, urban setting, and is not subject to a Williamson Act contract, on
open space easement, a conservation easement, or an agricultural conservation easement. The
surrounding land uses and resulting parcels would not support agricultural uses; the resulting parcels
would result in commercial development not incidental to commercial agricultural use of the land.
SECTION 2 DETERMINATION
NOW, THEREFORE, BE IT FURTHER RESOLVED that the Planning Commission of the City of South San
Francisco hereby makes the findings contained in this Resolution and recommends that the City Council
approval the entitlements request for 180 ECR Residential/R&D Project (P21-0126, UP21-0013, DR21-0045,
TDM21-0012, and PM21-0003) subject to the attached Conditions of Approval.
BE IT FURTHER RESOLVED that the resolution shall become effective immediately upon its passage and
adoption.
* * * * * * *
City of South San Francisco Page 8 of 9
Attest:__________________________________
Tony Rozzi
Secretary to the Planning Commission
I hereby certify that the foregoing resolution was adopted by the Planning Commission of the City of
South San Francisco at a regular meeting held on the 18th day of August, 2022 by the following vote:
AYES:
NOES:
Chair Shihadeh, Vice Chair Tzang, De Paz Fernandez, Faria, Funes, Evans, Murphy
______________________________________________________________
ABSTENTIONS:
ABSENT:
______________________________________________________________
________________________________________________________
* * * * * * *
City of South San Francisco Page 9 of 9