HomeMy WebLinkAboutReso 3350-1961RESOLUTION NO. 3350
A RESOLUTION OF THE CITY COUNCIL OF THE ~ITY OF
SOUTH SAN FRANCISCO APPROVING ALTERATIONS AND
CHANGES IN WORK IN ACCORDANCE WITH CONTRACT --
SOUTH SAN FRANCISCO MARINA
BE IT RESOLVED by the City Council of the City of South San Francisco
that the proposed alterations and changes as permitted by Section 15 of the a~ree-
ment between the City and'Healy Tibbitts Construction Company for the construction
of the South San Francisco Marina contained in change order No. 1, a copy of which
is attached hereto as Exhibit A, shall stand approved upon approval by the Small
Craft Harbor Commission or its representative and acceptance by contractor Healy
Tibbitts Construction Company.
I hereby certify that the foregoing resolution was regu-
larly introduced and adopted by the City Council of the City of
South San Francisco at au adjourned regular meetin~ held ou the 6th
day of December, 1961, by the following vote:
Ayes, Councilmen
Ncc s, "
Absent,
G. J. Rozzi, Patrick E. Ahern, Emilio Cortesi,
Andrew Rocca, and Leo J. Ryan.
None.
None.
ATTEST:
ARTHUR A. RODONDI
City Clerk
334
"Exhibit A"
Order No.:
CITY OF SOUTH SAN FRANCISCO
CHANGE ORDER
1
To the Contractor:
Address:
Date: December 6~ 1961
Building or Job: SOUTH SAN FRANCISCO MARINA
Healy Tibbitts Construction Co.
411 Brannan Street, San Francisco, California
You are hereby instructed that the contract in caption is modified as
herein specifically set forth, but that in all other respects the contract remains
unaltered.
Chan~e Item Description Quantit.¥ Unit Bid Extension
NORTH BREAKWATER
Delete 3 N. Brkwtr. Sect.
w/40' B Piles
Add 6 Select Fill
Add 9 Rock Armor,
Class B
25o ~F $ 120.00 -$30,000
9,500 Ton $ 1.50
600 Ton $ 4.00 / 2,.~00
North Breakwater Subtotal -$13,350
UTILITIES
Delete 27
Delete 28
Delete 29
8" Sewer
Sanitary Manhole
Sanitary Lift Station
1,000 LF $ 23.00
3 Ea. $ 500.00
1 Ea. $ 8~00.00
Utility Subtotal
- 1,500
- 8,000
-$32,5oo
DEDUCT:
Total Change
Original Bid
-$45,85o
$691,692
REVISED C0NTHACT $6~5,842
Per Change Order
FORTY-FIVE THOUSAND, EIGHT HUNDP~ED FIFTY AND N0/IO0 DOLLARS ($45,850.00).
J. A. BLUM~ & ASSOCIATES, ENGINEERS
DIRECTOR OF PUBLIC WORKS
In accepting an order for extras or deductions, !t is expressly agreed
by the Contractor that the time for completing the building shall not be extended,
and that this order shall not in any way alter the terms of the contract except as
herein specfflcally provided, or release or exonerate any surety on any bond given
to secure the performance of this contract.
APPROVED:
Mayor
ACCEPTED:
HEALY TIBBITTS CONSTRUCTION CO.
(Contractor)
By
This Change Order is approved by the Division of Small Craft Harbors, Department of
Parks and Recreation.