HomeMy WebLinkAbout15 Ch 5_Alternatives DEIR 10 12 18.pdf5. Alternatives
5 ALTERNATIVES
5.1 Introduction
Chapter 5, Alternatives, evaluates alternatives to the proposed project and examines the potential
environmental impacts associated with each alternative. By comparing these alternatives to the proposed
project, the relative environmental advantages and disadvantages of each may be analyzed and weighed.
California Environmental Quality Act (CEQA) Guidelines section 15126.6(a) states that an environmental
impact report (EIR) must describe and evaluate a reasonable range of alternatives to the proposed project
which would feasibly attain most of the proposed project's basic objectives but would avoid or
substantially lessen any identified significant adverse environmental impacts of the proposed project.
The range of alternatives required in an EIR is governed by a "rule of reason" that requires the EIR to set
forth only those potentially feasible alternatives necessary to foster informed public participation and an
informed and reasoned choice by the decision - making body (CEQA Guidelines section 15126.6(f)).
Therefore, an EIR does not need to address every conceivable alternative or consider infeasible
alternatives. CEQA generally defines "feasible" to mean the ability to be accomplished in a successful
manner within a reasonable period of time, taking into account economic, environmental, social,
technological, and legal factors (CEQA Guidelines section 15364). The following factors may also be
considered: site suitability, economic viability, availability of infrastructure, general plan consistency,
other plans or regulatory limitations, jurisdictional boundaries, and the ability of the proponent to attain
site control (CEQA Guidelines section 15126.6(f)(1)). An EIR does not need to consider an alternative
whose effect cannot be reasonably ascertained and whose implementation is remote and speculative
(CEQA Guidelines, Section 15126.6(f)(3)).
Two alternatives are evaluated in this chapter:
• Alternative A: No Project Alternative
• Alternative B: Reduced Development Alternative
Under Alternative A: No Project Alternative, the existing land uses and site conditions at the project site
would not change, and the project site would not be rezoned to Business Technology Park (BTP) and the
floor area ratio (FAR) would remain 0.4 or 1.0 for the various parcels. Alternative B: Reduced
Development Alternative would comply with the existing City of South San Francisco (City) zoning code
and regulations established for this site. Under this alternative, the project site would remain in a Business
Commercial (BC) district on one parcel (Assessor's Parcel Number [APN] 015- 102 -250), and a Mixed
Industrial district on the remaining seven parcels (APNs 015- 102 -230, 015 -102 -210, 015- 102 -220,
015- 102 -180, 015 -102 -160, 015- 102 -240, and 015- 102 -290).
201 Haskins Way Project Draft EIR 5.1 October 12, 2018
5. Alternatives
Table 5.1: Comparison of Characteristics of the Proposed Project to the Alternatives and Table 5.2:
Comparison of Significant Impacts of the Proposed Project to the Alternatives, shown below on
pp. 5.3 -5.4, compare the main features and impacts of the proposed project to those of the alternatives.
Alternative B would reduce the project -level impact on one intersection but not to a less - than - significant
level; this impact would remain significant and unavoidable (see Impact TR -2). Alternative B would
reduce the project's contribution to a significant cumulative impact to a less- than - significant level for six
intersections and would reduce queue - related traffic impacts (see Impacts C -TR -3, C -TR -5 [Phase 1
only], C- TR -10, C- TR -11, C- TR -12, and C- TR -13), one freeway segment impact (see Impact C- TR -19),
and one freeway ramp impact (see Impact CR -20 [Phase 1 only]). Alternative B would also reduce the
proposed project's contribution to 12 significant cumulative transportation impacts but not to a less -than-
significant level; these impacts would remain significant and unavoidable (see Impacts C -TR -4, C -TR -5
[buildout only], C -TR -6, C -TR -7, C -TR -8, C -TR -9, C- TR -15, C- TR -16, C- TR -17, C- TR -18, C -TR -20
[buildout only], and C- TR -21). This alternative would reduce less- than - significant air quality, greenhouse
gas (GHG) emissions, land use, noise and vibration, and utilities impacts of the proposed project, which
are analyzed below. This alternative would result in similar less- than - significant impacts on biological
resources, cultural resources, hydrology and water quality, and impacts listed in Section 4.11 (aesthetics,
agriculture and forest resources, geology and soils, hazards and hazardous materials, mineral resources,
and recreation) to those with the proposed project, which are analyzed below. This chapter identifies the
Reduced Development Alternative as the environmentally superior alternative (i.e., the alternative that
would result in the least adverse effect on the physical environment). This chapter concludes with a
discussion of the alternatives that were considered but not analyzed further because they were rejected as
infeasible or failed to meet the basic project objectives.
The project sponsor's objectives for the proposed project in furtherance of the City's General Plan and
City's policies for developing the East of 101 Area are presented in Chapter 3, Project Description, pp.
3.2 -3.3. The ability of each alternative to meet these objectives is presented in Table 5.3: Ability of
Alternatives to Meet Project Objectives.
As shown in the table, the No Project Alternative (Alternative A) would not meet any of the basic project
objectives. The Reduced Development Intensity Alternative (Alternative B) would only attain several of
the project sponsor's objectives to a lesser or partial extent. For example, this alternative would provide
less office /research and development (R &D) development than the proposed project (459,514 gross
square feet [gsf] with the alternative, compared to 677,600 gsf with the proposed project), and would not
maximize the opportunity to increase office /R &D uses in an area designated for the promotion of new
biotechnology and research and development. Due to the reduced allowable development under
Alternative B, it would not result in the degree of positive fiscal impact on the City through the creation
of jobs, enhancement of property values, and generation of property tax and other development fees.
201 Haskins Way Project Draft EIR 5.2 October 12, 2018
Chapter 5. Alternatives
Table 5.1: Comparison of Characteristics and Significant Impacts of the Proposed Project to the Alternatives
Parcel Address Lot Size Alternative A: No Project Alternative' Proposed Project
Alternative B: Reduced Development Potential Alternative'
(APN) (sq. ft.)
Total Floor Area Total Floor Area
Gross Square Feet
Total Floor Area Gross Square Feet°
Phase 1 Area Phase 2 Area Total Existing Phase 1 Phase 2 Project Phase 1
Phase 2
Project
Phase 1 Phase 2 Project Phase 1 Phase 2
Project
Existing Existing Development Development Development Buildout Development
Development
Buildout
Development Development Buildout Development Development
Buildout
Development Development (sq. ft.) (sq. ft.) (sq. ft.) (sq. ft.) (gsf)
(gsf)
(gsf)
(sq. ft. (sq. ft.) (sq. ft.) (gsf) (gsfJ
(gsf)
(sq. ft.) (sq. ft.)
201 Haskins Way
280,765 24,075 - 24,075 280,765 - 280,765 311,368
-
311,368
168,459 - 168,459 186,990 -
186,990
(015- 102 -230)
400 -450 East
Jamie Court (015- 267,000 157,000 - 157,000 25,000 85,000',2 110,00012 25,000
85,000'
110,000
25,000 85,000',2 110,0001 ,2 25,000 85,000'
110,000
102 -250)
101 Haskins Way
24,535 - 7,000 7,000 - 24,535 24,535 -
25,762
25,762
- 14,721 14,721 - 16,340
16,340
(015- 102 -210)
151 Haskins Way
28,602 11,599 11,599 - 28,602 28,602 -
30,032
30,032
- 17,161 17,161 19,049
19,049
(015- 102 -220)
410 East Grand
Avenue 40,384 27,300 27,300 - 40,384 40,384 -
42,403
42,403
- 24,230 24,230 26,895
26,895
(015- 102 -180)
430 East Grand
Avenue 72,076 - 37,096 37,096 - 72,076 72,076 -
75,680
75,680
- 43,246 43,246 - 48,003
48,003
(015- 102 -160)
451 East Jamie
Court 62,087 75,000 75,000 - 62,087 62,087 -
65,191
65,191
- 37,252 37,252 - 41,350
41,350
(015 -102 -240)
(015- 102 -290) 16,347 - - - - 16,347 16,347 -
17,164
17,164
- 9,808 9,808 - 10,887
10,887
Total 791,796 181,075 157,995 339,070 305,765 329,031 634,796 336,368
341,232
677,600
193,459 231,418 424,877 211,990 247,524
459,514
Existing Parking 464 114 578 424
424
424
424
Spaces to - - - -
-
- - - -
Remain spaces spaces spaces spaces
spaces
spaces
spaces
New Parking 903
603
1,506
605 707
1,312
Spaces - Spaces
Spaces
spaces
spaces spaces
spaces
Total Parking 464 114 578 1,327
603
1,930
1,029 707
1,736
Spaces spaces spaces spaces Spaces
Spaces
spaces
spaces spaces
spaces
Notes:
' Existing floor area that would remain under Alternative A is based on the FAR - defined square footage of development for the land use analysis purposes. For Transportation analysis
and other quantitative environmental analyses, development impacts are calculated based on gross square feet. Therefore, this table provides
both FAR - defined floor area and gross square feet.
2 The 110,000 sq. ft. of available floor area at 400 -450 East Jamie Court would be developed through construction of the planned approximately 25,000 sq. ft. building addition to 400
-450
East Jamie Court plus the remaining development potential of BTP use under Phase 2. When the total floor area of the Phase 1 building
addition is determined, the remaining balance of floor area would be applied to the design of the BTP use under Phase 2 development. It is assumed that the total floor area of the building
addition is approximately 25,000 sq. ft of floor area. Therefore, for the purposes of plan -level analysis, it is assumed that Phase 2
development would result in, at minimum, 85,000 sq. ft. total floor area of BTP use.
2 Section 20.040.008 of the zoning ordinance specifies that floor area includes, but is not limited to, habitable (as defined in the California Building Code) basements and cellars that
are below the roof and within the outer surface of the main walls of principal or accessory buildings or the centerlines of party walls separating
such buildings or portions thereof or within lines drawn parallel to and two feet within the roof line of any building without walls. In the case of a multi -story building that has
covered or enclosed
stairways, stairwells or elevator shafts,
the horizontal area of such features shall be counted only once at the floor level of their greatest
area of horizontal extent. The ordinance specifies that floor area does not include mechanical, electrical, and communication equipment rooms that do not exceed two percent of the building's
gross floor area; bay
windows or other architectural projections where the vertical distance between the lowest surface of the projection
and the finished floor is 30 inches or greater;
201 Haskins Way Project Draft EIR 5.3 October 12, 2018
5. Alternatives
Table 5.2: Comparison of Significant Impacts of the Proposed Project to the Alternatives
Impact Statement
Alternative A: No Project Proposed Project Alternative B: Reduced
Alternative Development Potential
Alternative
Summary of Significant Impacts of the No Project, the Proposed Project, and the Reduced Project Alternative
Legend: NI = No Impact; LS = Less than Significant; LTSM = Less than Significant with Mitigation; SU = Significant and unavoidable; SUM = Significant and unavoidable impact
with mitigation; NA = Not Applicable
Section 4.9: Transportation and Circulation- Project Impacts
TR -2: The proposed project (Phase 1 or buildout) would cause the intersection
NI SU SU
of Allerton Avenue and East Grand Avenue to exceed LOS D operations
during the PM peak hour, and the project would contribute more than 2
percent of the total traffic through the intersection.
Section 4.9: Transportation and Circulation - Cumulative Impacts
C -TR -3: Buildout of the proposed project (Phases 1 & 2) would contribute
NI SU LTS
considerably to the significant impact at the intersection of Airport Boulevard
and Grand Avenue during the AM peak hour.
C -TR -4: Buildout of the proposed project (Phases 1 & 2) would contribute
NI SU SU
considerably to a significant cumulative at the intersection of Dubuque Avenue
and Grand Avenue during the PM peak hour.
C -TR -5: The proposed project (Phase 1 or buildout) would contribute
NI SU LTS (Phase 1)
considerably to a significant cumulative impact the intersection of East Grand
SU (buildout)
Avenue and Grand Avenue Overcrossing during the PM peak hour.
C -TR -6: The proposed project (Phase 1 or buildout) would contribute
NI SU SU
considerably to a significant cumulative impact at the intersection of Gateway
Boulevard and East Grand Avenue during the PM peak hour.
C -TR -7: The proposed project (Phase 1 or buildout) would contribute
NI SU SU
considerably to a significant cumulative impact at the intersection of Harbor
Way /Forbes Boulevard and East Grand Avenue in both the AM and PM peak
hours.
C -TR -8: The proposed project (Phase 1 or buildout) would contribute
NI SU SU
considerably to a significant cumulative at the intersection of Littlefield Avenue
and East Grand Avenue in the AM peak hour.
C -TR -9: The proposed project (Phase 1 or buildout) would contribute
NI SU SU
considerably to a significant cumulative impact at the intersection of Allerton
Avenue and East Grand Avenue in the PM peak hour.
C -TRA 0: The proposed project at buildout would contribute considerably to a
NI SU LTS
significant cumulative impact at the intersection of Airport Boulevard /Produce
Avenue /San Mateo Avenue in the PM peak hour.
C -TRA 1: The proposed project at buildout would contribute considerably to a
NI SU LTS
significant cumulative impact at the intersection of Gateway Boulevard /South
Airport Boulevard /Mitchell Avenue in the PM peak hour.
C- TR -12: The proposed project at buildout would contribute considerably to a
NI SU LTS
significant cumulative impact at the freeway ramp intersection of South Airport
Boulevard and U.S. 101 Northbound Hook Ramps /Wondercolor Lane in the
AM peak hour.
C- TR -13: The proposed project at buildout would contribute considerably to a
NI SU LTS
significant cumulative impact at the intersection of South Airport Boulevard
and Utah Avenue in the AM peak hour.
C -TRA5: The proposed project (Phase 1 or buildout) would add more than 1
NI SU SU
percent of total traffic and therefore would contribute considerably to the
significant cumulative impacts on the southbound left turn movement in the
AM peak hour and the westbound right -turn movement in the AM and PM
peak hours at the intersection of Airport Boulevard and Grand Avenue where
the 95th percentile queues with future cumulative growth in 2040 would exceed
the available storage length without the project.
C -TRA6: The proposed project (Phase 1 or buildout) would add more than 1
NI SU SU
percent of total traffic and therefore would contribute considerably to the
significant cumulative impacts on the eastbound and westbound through
movements in the PM peak hour and westbound left turn movement in the AM
and PM peak hours on East Grand Avenue at Gateway Boulevard where the
95th percentile queues would exceed the available storage lengths during
these peak hours without the proposed project.
C- TR -17: The proposed project (Phase 1 or buildout) would add more than 1
NI SU SU
percent of total traffic and therefore would contribute considerably to the
significant cumulative impact on the westbound left turn movement on Airport
Boulevard at the intersection of Airport Boulevard /Produce Avenue where the
95th percentile queue would exceed the available storage length during the AM
and PM peak hours in 2040 without the proposed project.
C- TR -18: The proposed project (Phase 1 or buildout) would add more than 1
NI SU SU
percent of total traffic and therefore would contribute considerably to the
significant cumulative impact on the eastbound left turn movement on the
northbound U.S. 101 off -ramp at South Airport Boulevard/Wondercolor Lane
where the 95th percentile queue would exceed the available storage length
during the AM peak hour in 2040 without the proposed project.
C- TR -19: The freeway segments serving the proposed project site would
NI SU LTS
operate at unacceptable LOS F in the future with forecast development in
2040, resulting in a significant cumulative impact. The proposed project at
buildout (Phases 1 & 2) \would add more than 1 percent of total traffic to two
freeway segments during the PM peak hour which would operate at LOS F
under cumulative conditions without the project.
C- TR -20. The proposed project (Phase 1 or Phases 1 & 2) would add more
NI SU LTS (Phase 1)
than 1 percent of total traffic and therefore would contribute considerably to
SU (buildout)
the significant cumulative impact on the northbound U.S. 101 off -ramp at
South Airport Boulevard /Wondercolor Lane where the volume would exceed
the available capacity during the AM peak hour in 2040 without the proposed
project.
C- TR -21. The proposed project (Phase 1 or Phases 1 & 2) would add traffic
NI SU SU
volumes which would cause total traffic to exceed capacity and therefore
would contribute considerably to the significant cumulative impact on the
southbound U.S. 101 on -ramp from Produce Avenue where the volume would
not exceed the available capacity during the PM peak hour in 2040 without the
proposed project.
201 Haskins Way Project Draft EIR 5.4 October 12, 2018
5. Alternatives
Table 5.3. Ability of Alternatives to Meet Project Objectives
Project Objective
Alternative A: No
Alternative B: Reduced
Project Alternative
Development Alternative
Would the alternative meet this objective?
Create state -of- the -art research and development facilities consistent
Partial: Alternative B does
with the General Plan designation of the site, and General Plan goals
not fully maximize
and policies.
No
allowable density under
the existing General Plan
land use designations
(CC /MI)
Promote the City's ongoing development of the East of 101 Area into a
nationally recognized biotechnology and research and development
No
Partial
center that will attract other life science uses.
Further the City's policies of developing the East of 101 Area with new
opportunities for continued evolution from manufacturing and
No
Partial
warehousing /distribution to biotechnology and research and
development.
Redevelop underutilized parcels within the project site at a higher
Partial: Alternative B does
density to take advantage of the opportunities offered in the East of
No
not fully maximize density'
101 Area to create a vibrant research and development campus.
Develop a research and development campus with a high level of
design quality as called for in the Design Policies and Guidelines of
No
Partial
the East of 101 Area Plan
Build a project that creates quality jobs for the City;
No
Less than the proposed
project
Provide sufficient space for tenants to employ key scientific and
Partial: Alternative B does
business personnel in proximity to each other to foster efficient
No
not fully maximize
collaboration and productivity;
allowable floor area'
Capitalize on the project's proximity to the City's Bay shoreline and
San Francisco Bay Trail (Bay Trail) by providing views and access to
No
Yes
the waterfront.
Enhance the visual quality of development around the Bay shoreline
No
Partial
and take advantage of the attractive setting it provides.
Promote alternatives to automobile transportation to further the City's
transportation objectives by emphasizing linkages, TDM, and
No
Yes
pedestrian access and ease of movement between buildings.
Enhance vehicular, bicycle, and pedestrian circulation and access in
No
Yes
the area surrounding the project site.
Build a project that is viable in the East of 101 Area based upon
NO
Less than the proposed
market conditions and project service requirements for the area.
project
Incorporate flexibility for office and research and development uses to
Less than the proposed
ensure that the project is responsive to tenant demands based on
No
project
market conditions
Provide a positive fiscal impact on the City through the creation of
Less than the proposed
jobs, enhancement of property values, and generation of property tax
No
project
and other development fees.
Retain the flexibility to build the project in phases that respond to
No
Yes
market conditions.
Allow for the continued operation of existing manufacturing and
warehousing /distribution uses until new development occurs,
No
Yes
consistent with City policies.
Note: ' Alternative B provides 32 percent of the Office /R &D space proposed for the project.
Source: ARE, City of South San Francisco (2018)
201 Haskins Way Project Draft EIR 5.5
October 12, 2018
5. Alternatives
5.2 Alternative A: No Project Alternative
CEQA Guidelines section 15126.6(e) requires that a "no project" alternative be evaluated: "The purpose
of describing and analyzing a no project alternative is to allow decision makers to compare the impacts of
approving the proposed project with the impacts of not approving the proposed project." CEQA
Guidelines section 15126.6(e)(2) requires that the no project alternative analysis "discuss the existing
conditions... as well as what would be reasonably expected to occur in the foreseeable future if the project
were not approved, based on current plans and policies and consistent with the available infrastructure
and community services." As noted in CEQA Guidelines section 15126.6, an EIR for "a development
project on identifiable property" typically analyzes a no project alternative, i.e., "the circumstance under
which the project does not proceed. Such a discussion would compare the environmental effects of the
property remaining in its existing state against environmental effects that would occur if the project is
approved. If disapproval of the project under consideration would result in predictable actions by others,
such as the proposal of some other project, this `no project' consequence should be discussed."
5.2.1 Description
Under Alternative A: No Project, the existing land uses and site conditions at the project site would not
change. The existing seven buildings on the project site would remain, as would the existing ingress and
egress points, and the surface parking which accommodates 578 vehicles, 20 semi - tractors, and 35
trailers. Under the No Project Alternative, the project site would not be rezoned to BTP and the FAR
would remain 0.4 or 1.0 for the various parcels. The No Project Alternative would not preclude potential
future development of the project site with a range of land uses that are permitted at the project site.
5.2.2 Impacts
This environmental analysis assumes that the existing structures and uses on the project site would not
change and that the existing physical conditions, as described in detail for each environmental topic in
Chapter 4, Environmental Setting, Impacts, and Mitigation, would remain the same. If the No Project
Alternative were implemented, none of the impacts associated with the proposed project, as described in
Chapter 4, would occur. However, development and growth would continue within the vicinity of the
project site as reasonably foreseeable future projects are approved, constructed, and occupied. These
projects could contribute to cumulative impacts in the vicinity, but under the No Project Alternative, land
use activity on the project site would not contribute to these cumulative impacts beyond existing levels.
AIR QUALITY
Under Alternative A there would be no demolition or construction activities and no new operational
sources of air pollutants on the project site. Existing stationary sources of air pollution near the project
site and major roadways contributing to air pollution in the project vicinity would remain in existing
conditions. Compared to the proposed project, which would result in less- than - significant project -level air
quality impacts with mitigation and a less than cumulatively considerable contribution to significant
cumulative air quality impacts with mitigation, the No Project Alternative would have no impact related
to air quality. Because potential air quality impacts that would occur under the proposed project would
201 Haskins Way Project Draft EIR 5.6 October 12, 2018
5. Alternatives
not occur under this alternative, implementing air quality mitigation measures MM -AQ -1 a through MM-
AQ -lb would not be necessary.
BIOLOGICAL RESOURCES
Under Alternative A there would be no demolition of buildings or removal of any trees or vegetation.
Compared to the proposed project, which would result in a less- than - significant project -level biological
resources impacts with mitigation and a less than cumulatively considerable contribution to significant
cumulative biological impacts with mitigation, the No Project Alternative would have no impact related
to biological resources. Because potential biological resources impacts that would occur under the
proposed project would not occur under this alternative, implementing mitigation measures MM -BI -la
through MM -BI -1 d would not be necessary.
CULTURAL RESOURCES
Under Alternative A no excavation and demolition of buildings would occur on the site. The site would
remain in its current condition. Compared to the proposed project, which would result in a less -than-
significant project -level cultural resources impacts with mitigation and a contribution to significant
cumulative cultural impacts that is less than cumulatively considerable with mitigation, the No Project
Alternative would have no impact related to cultural resources. Because potential cultural resources
impacts that would occur under the proposed project would not occur under this alternative, implementing
mitigation measures MM -CR -2a through MM- CR -2c, and MM -CR -3, would not be necessary.
Crl:7 � � � I. [�1�I+9 �[r7_E•'�;h�il6'%�[�7►[+'?
Alternative A would not result in new GHG emissions. No demolition or new construction activities
would occur. There would be no new development to adhere to Leadership in Energy and Environmental
Design (LEED) requirements. Sources of GHG emissions would continue under existing conditions but
there would be no cumulatively considerable contribution to significant GHG impacts.
HYDROLOGY AND WATER QUALITY
Under Alternative A, there would be no demolition or construction of new buildings, and no changes to
existing impervious surfaced, hardscape, or landscaped and vegetated areas on the project site. The No
Project Alternative would not alter the site drainage pattern or substantially deplete groundwater supplies,
or interfere substantially with groundwater recharge. Compared to the proposed project, which would
result in a less- than - significant project -level hydrology and water quality impact and a less -than-
cumulatively considerable contribution to significant cumulative hydrology and water quality impacts, the
No Project Alternative would have no impact related to hydrology and water quality.
LAND USE AND PLANNING
The No Project Alternative would not involve a rezoning of the parcels on the project site. The project
site would remain zoned as Business Commercial on one parcel (APN 015- 102 -250), and as Mixed
Industrial on the remaining seven parcels (APNs 015- 102 -230, 015 -102 -210, 015 -102 -220, 015- 102 -180,
201 Haskins Way Project Draft EIR 5.7 October 12, 2018
5. Alternatives
015 -102 -160, 015- 102 -240, and 015- 102 -290). Under the No Project Alternative, land use would remain
as under existing conditions. Compared to the proposed project, which would result in a less -than-
significant project -level land use and planning impact and a less- than - significant cumulatively
considerable contribution to significant cumulative land use and planning impact, the No Project
Alternative would have no impact related to land use and planning.
NOISE
Under the No Project Alternative, there would be no demolition or construction activities and no new
temporary or operational noise or vibration impacts in the project vicinity or within the project site. Noise
conditions in the area would remain as in existing conditions. Compared to the proposed project, which
would result in less- than - significant project -level noise impacts with mitigation and a less than
cumulatively considerable contribution to cumulative noise impacts with mitigation, the No Project
Alternative would have no impact related to noise. Because potential noise impacts that would occur
under the proposed project would not occur under this alternative, implementing noise mitigation
measures MM -NO -2 and MM -NO -3 would not be necessary.
TRANSPORTATION AND CIRCULATION
Unlike the proposed project, under the No Project Alternative there would be no changes to traffic and
circulation. The existing commercial and industrial buildings on the project site would continue to operate
in their current condition and traffic conditions under existing conditions would remain. Compared to the
proposed project, which would result in a significant and unavoidable project -level transportation and
circulation impact and a cumulatively considerable contribution to significant unavoidable cumulative
transportation and circulation impacts, the No Project Alternative would have no impact related to
transportation and circulation. Because the impacts that would occur under the proposed project would
not occur under this alternative, mitigation measures would not be applicable.
UTILITIES AND SERVICE SYSTEMS
The No Project Alternative would not involve any new construction or new land uses on the project site.
This alternative would not alter the existing stormwater conveyances and would not exceed the capacity
of the wastewater treatment provider serving the project site. This alternative would also not require the
construction of new, or expansion of existing, wastewater treatment facilities. The No Project Alternative
would not require the construction of new, or expansion of existing, stormwater drainage facilities, the
construction of which could cause significant environmental effects. Compared to the proposed project,
which would result in a less- than - significant project -level utilities and service systems impact and a less -
than- cumulatively considerable contribution to significant cumulative utilities and service systems
impact, the No Project Alternative would have no impact related to utilities and services systems.
OTHER TOPICS
The Draft EIR concludes that the proposed project would have no impact or less- than - significant impacts
in the following analysis areas:
201 Haskins Way Project Draft EIR 5.8 October 12, 2018
5. Alternatives
• Agriculture and Forest Resources (all topics)
• Aesthetics (all topics)
• Geology and Soils (all topics)
• Hazards and Hazardous Materials (all topics)
• Mineral and Energy Resources (all topics)
• Population and Housing (all topics)
• Public Services (all topics)
• Biological Resources (all topics)
• Recreation (all topics)
The No Project Alternative would result in no impact related to any of the above - listed environmental
topics, because this alternative would result in no changes to existing site conditions.
5.3 Alternative B: Reduced Development Alternative
5.3.1 Description
Unlike the proposed project, Alternative B: Reduced Development Alternative, would comply with the
existing City zoning code and regulations established for this site. Under this alternative, the project site
would remain zoned as Business Commercial on one parcel (APN 015 -102 -250), and as Mixed Industrial
on the remaining seven parcels (APNs 015 -102 -230, 015- 102 -210, 015- 102 -220, 015 -102 -180, 015 -102-
160, 015- 102 -240, and 015- 102 -290). Under existing zoning, parcels would provide new office/R &D
development potential of up to 1.0 FAR for the Business Commercial District, similar to the proposed
BTP use under the proposed project. Under existing zoning, the Mixed Industrial district provides a new
office/R &D development potential of 0.4 FAR, or up to 0.6 FAR with development and implementation
of a Transportation Demand Management (TDM) Plan and design and green building standards, subject
to approval of a Conditional Use Permit (CUP). As a result, Alternative B would include approximately
459,514 gsf of office /R &D development, 218,086 gsf less than under the proposed project overall, as
shown in Table 5. 1, on p. 5.3.
Similar to the proposed project, Alternative B would involve the removal of existing light industrial uses
and associated parking on seven parcels (101, 151, and 201 Haskins Way; 410 and 430 East Grand
Avenue; 451 East Jamie Court; and one parcel with no address [APN 015- 102 - 290]), the construction of
new office/R &D use on those seven parcels, and the expansion of existing office/R &D use on one parcel
(400 -450 East Jamie Court), as shown on Figure 5.1: Alternative B - Reduced Development
Alternative — Conceptual Site Plan. Like the proposed project, this alternative would be constructed
using at least two development phases. For the purposes of analysis under CEQA, the EIR considers a
Phase 1 site plan and conceptual Phase 2 site plan. Alternative B would result in the construction of
approximately 193,459 square feet of office/R &D use during Phase 1 development, and approximately
231,418 square feet during Phase 2 development.
201 Haskins Way Project Draft EIR 5.9 October 12, 2018
U
N
O Co m
¢ ¢
N �— N
p w Co
2 N � �
a` n a a
c 4M �l 0
� ® II
J ® II
c
CD CL
Q4�D CD
I .
ti
II- cc
-
a�
Cu
N 0) 0)
c c
w
cc
Cl) > %� Q
z Y N W m }
> m
W I I L J
Cl) J m
¢ CrJI� a M O
U
U
C7
� N
C/) LL
W Z
�M
El
70 J
Co 000000 >
m 0
70 _ -0 C C
Q N
-------- O N ) X m E2
i� > - W m t-
..N fn LLl N
LLI > L , ¢ m
m
J O
F U
c7 0 U) N
N w v
C
f6
b 11
�. U)
HASKINS WAY
F�
201 Haskins Way Project Draft EIR 5.10 October 12, 2018
�vJ
I�
09
tc-
Q
�- Z
Z Q
CW J
C �
CL. W
O�
J
W
> J
W ¢
LW LW
U U
Z Z
DO
W V
m
LU
m >
f- Z
¢ ce
Z W
Cz J
W Q
J
Q
Ln
W
V
W
5. Alternatives
Like the proposed project, this alternative would involve construction of two primary office /R &D
buildings: the 201 Haskins Way Building under Phase 1 development, and the conceptual East Grand
Building under Phase 2 development at project buildout. However, the density of the development would
be reduced and each building would be constructed to a maximum height of three stories, as compared to
five stories under the proposed project. In addition, the conceptual East Grand Building in the Phase 2
area would have a slightly smaller development footprint. Similarly, the proposed parking garage would
also be reduced to three stories under Alternative B, as compared to five stories under the proposed
project. See Figure 5.2: Alternative B — Reduced Development Alternative 201 Haskins Way
Building Elevations and Figure 5.3: Alternative B — Reduced Development Alternative Conceptual
East Grand Avenue Building Elevations.
Under existing Business Commercial zoning, the 400 -450 East Jamie Court parcel would have the
development potential of 1.0 FAR, the same as for the proposed project. Accordingly, Alternative B
would also involve construction of a 25,000 gsf building addition on the 400 -450 East Jamie Court parcel
during Phase 1. As with the proposed project, Phase 2 development on the 400 -450 East Jamie Court
parcel is conceptual. Because detailed information about Phase 2 development is not known at this time,
the EIR considers the maximum potential development that could occur under existing zoning. Phase 2
development would require subsequent project -level site design review. For illustrative purposes, the EIR
includes a conceptual Phase 2 development plan. As with the proposed project, the Phase 2 development
plan would include future office/R &D development capacity of up to approximately 85,000 square feet of
floor area on the 400 -450 East Jamie Court parcel (APN 015- 102 -250).
As with the proposed project, the existing driveways would be removed and four new driveways would
be constructed: two new driveways on Haskins Way, one new driveway on East Jamie Court, and one
new driveway on East Grand Avenue, as shown on Figure 5. 1, p. 5.10. At project buildout, Alternative B
would provide 1,312 off - street parking spaces in surface parking lots and a three -story parking garage on
the site, reduced from 1,930 spaces with a five -story parking garage under the proposed project. See
Figure 5.4: Alternative B — Reduced Development Alternative Conceptual Parking Structure
Elevations at Project Buildout. The surface parking lot constructed in the Phase 2 area would be
slightly larger than under the proposed project to account for a smaller conceptual East Grand Building
footprint.
Similar to the proposed project, Alternative B would include the same overall pedestrian and landscape
improvements to the site. New sidewalks with street trees and landscaping buffers would be constructed
along East Jamie Court, Haskins Way, and East Grand Avenue. Like the proposed project, this alternative
would include at least 15 percent of lot coverage for landscaping and a similar number of new street trees
would be planted to the site. Both of the proposed office /R &D buildings (the 201 Haskins Way Building
and the conceptual East Grand Building) would include showers and clothes locker facilities, and short-
term and long -term bicycle parking spaces in accordance with the State's Title 24 Green Building
Standards (CALGreen) Section 5.106.4.1.2, and would meet LEED Version 4 bicycle parking standards.
201 Haskins Way Project Draft EIR 5.11 October 12, 2018
201 Haskins Way Project Draft EIR 5.12 October 12, 2018
0
fte
Q
Q
W V]
Z
�O
Q �
ZQ
W iy
-.J J
Q W
F, U
Z Z
CW Q
L J
a —
O�
W
6 Q
0 �
W Z
U Y
� Q
W
r
� O
m N
W
Q
Z
w
W
J
Q
N
N
W
_U
W
201 Haskins Way Project Draft EIR 5.13 October 12, 2018
0
fte
Q
Q
W V]
>Z
�O
Q �
ZQ
W iy
-.J J
Q W
F, U
Z Z
CW Q
L J
a —
O�
W Q
W Z
� Q
D �
W U
U
W
W
a/ J
i Q
m
W
> W
— U
Q Z
Z
� V
W
H
J
Q
M
N
W
_U
W
a
d
O
Q
a �
fte
z�a
Q
Z
a
201 Haskins Way Project Draft EIR 5.14 October 12, 2018
W �-
�O
Q
Z J
W
� CO
J
Q ~
WO
J Q
W C'n
> Z
WO
0 ~
W Q
U ,Lw
J
Q W
W W
i
CC ~
U
W
Q �
Z V
°C Z_
W
� Y
Q Y
N J
Q
W
V W
U
"" Z
O
U
5. Alternatives
Infrastructure activities associated with Alternative B would be similar to those described for the
proposed project. The project site is serviced by existing potable water, stormwater, sanitary sewer,
natural gas, electric, and trash and recycling services. New on -site facilities would be connected to
existing services along East Grand Avenue, Haskins Way, and East Jamie Court. No expansion or
increased capacity of off -site infrastructure would be necessary.
Construction activities associated Alternative B would be similar to those described for the proposed
project. Build -out of this alternative would be similar to the proposed project, and is assumed to occur
over two phases and approximately 4 years after project entitlements, if executed from start to finish.
Construction would not commence until the existing uses within each phase area have vacated. As with
the proposed project, Phase 1 development under Alternative B is anticipated to take approximately 18
months after project entitlements. The preliminary construction schedule assumes 2019 as the start of
construction and 2021 as the end of construction.
Under existing zoning, Alternative B would allow the existing uses in the Phase 2 area to continue. At
this time, no specific Phase 2 development is proposed, and it is uncertain when or if such development
would occur. As with the proposed project, it is assumed for purposes of this EIR that Phase 2
construction would commence in 2021 (immediately after completion of Phase 1 construction) and would
occur over an 18 -month period. Construction would not commence until the existing uses have vacated.
As for discretionary approvals, unlike the proposed project Alternative B would not involve zoning map
amendments. However, this alternative would still require a CUP, TDM Plan approval, design review,
and subdivision maps. Alternative B would also require standard City engineering, building, and fire
permits, along with other agency approvals (Bay Area Regional Water Quality Control Board, Bay Area
Air Quality Management District (BAAQMD), San Mateo County Department of Environmental Health,
Federal Aviation Administration, and the San Francisco Bay Conservation and Development
Commission). Because this alternative would not involve rezoning, the proposed project would not
require referral to the Airport Land Use Commission.
5.3.2 Impacts
The impact analysis below focuses on those impacts that were determined to be potentially significant
under the proposed project. Less than significant impacts are generally discussed only if implementation
of the alternative would substantially increase the impact.
Reducing the allowable office /R &D development to the amount currently allowed under existing zoning
(i.e., a reduction of 218,086 gsf) would primarily reduce impacts related to vehicle trips and, to some
degree, construction -period impacts, such as air pollutant emissions, traffic, and noise. Alternative B
would also avoid considerable contribution to significant and unavoidable impacts due to the reduced
number of vehicle trips for Impacts C -TR -3, Impact C -TR -5 (Phase 1 only), Impact C -TR -10 (buildout),
Impact C -TR -11 (buildout), Impact C -TR -12 (buildout), Impact C -TR -13 (buildout), Impact C -TR -19
(buildout), and Impact C -TR -20 (Phase 1 only). However, Alternative B would not, as discussed below,
result in the avoidance or lessening of any other significant and unavoidable impacts to a less -than-
201 Haskins Way Project Draft EIR 5.15 October 12, 2018
5. Alternatives
significant level (Impacts TR -2, C -TR -4, C -TR -5 [buildout only], C -TR -6, C -TR -7, C -TR -8, C -TR -9, C-
TR-15, C- TR -16, C- TR -17, C- TR -18, C -TR -20 [buildout only], and C- TR -21).
AIR QUALITY
Because this alternative would involve a reduction of 218,086 gsf compared to the proposed project,
Alternative B would result in fewer vehicle trips to the site than the proposed project as well as less
building space that would require water and energy use. This alternative would marginally reduce the
already less - than - significant air quality impacts identified under the proposed project.
Less building space under Alternative B would equate to marginally lower construction- period emissions,
though BAAQMD fugitive dust and emissions reduction measures would be required to reduce the
impact to less than significant, as under the proposed project.
As with the proposed project, impacts that can be brought to a less- than - significant level through
mitigation would also be marginally reduced. Mitigation Measures AQ -la and AQ -lb, would continue to
apply to Alternative B and would reduce project -level air quality impacts and the less than cumulatively
considerable contribution to significant air quality impacts to less - than - significant levels.
BIOLOGICAL RESOURCES
Because Alternative B would involve a similar development footprint, demolition, and excavation
program as the proposed project, impacts on biological resources during the construction period would
remain largely the same. Removal of existing light industrial buildings and on -site landscaping would be
expected to have the same impacts on wildlife species such as migratory birds and roosting bats.
Mitigation Measure MM- BI -la: Pre - Construction Nesting Bird Surveys and Buffer Areas, MM BI -lb:
Lighting Measures to Reduce Impacts to Birds, MM- BI -lc: Building Design Measures to Minimize Bird
Strike Risk would continue to apply to Alternative B and would reduce impacts to a less -than significant-
level. Mitigation Measure BI -Id: Pre - construction Bat Survey for Roosting Bats and Roosting Habitat
Abatement (Phase 2), would continue to apply to Alternative B during Phase 2 development for project
buildout and would reduce project -level impacts to a less -than significant- level. Mitigation Measure
BI -Id would also reduce Alternative B's cumulatively considerable contribution to significant biological
resources impacts to less- than - significant levels. Removal of any protected trees as defined under the
City's Tree Preservation Ordinance would be required to comply with the Tree Preservation Ordinance
under Alternative B and impacts would continue to be less than significant. As with the proposed project,
impacts that can be brought to a less- than - significant level through mitigation would also be marginally
reduced. Mitigation Measures MM- BI -la, MMBi -lb, MM- BI -lc, and MM -BI -Id continue to apply to
Alternative B and would reduce project -level impacts and reduce the less than cumulatively considerable
contribution to cumulative impacts.
CULTURAL RESOURCES
Alternative B would involve a similar excavation program as the proposed project, and impacts on
cultural resources during the construction period would remain largely the same. Excavation activities
could encounter archeological resources such as shell mounds, as identified in Impact CR -2, or other
201 Haskins Way Project Draft EIR 5.16 October 12, 2018
5. Alternatives
previously unrecorded archaeological resources. Mitigation Measures MM- CR -2a: Cultural Resources
Worker Environmental Awareness Program (WEAP), MM- CR -2b: Cultural Resources Monitoring
During Ground Disturbing Activities, and MM- CR -2c: Halt Construction Activity, Evaluate Find and
Implement Mitigation would continue to apply to Alternative B and would reduce impacts on
archaeological resources to a less- than - significant level. Application of the same mitigation measures
would also ensure that impacts associated with tribal cultural resources would be reduced to a less -than-
significant level under Alternative B. Application of MM -CR -3: Halt Construction Activity, Evaluate
Remains and Take Appropriate Action in Coordination with Native American Heritage Commission
would continue to apply to Alternative B and would reduce impacts associated with the potential
inadvertent discovery of human remains to a less- than - significant level. As with the proposed project,
Mitigation Measures MM- CR -2a, MM- CR -2b, MM- CR -2c, and MM -CR -3 would continue to apply to
Alternative B and would reduce project -level impacts and reduce the less than cumulatively considerable
contribution to cumulative impacts.
GREENHOUSE GAS EMISSIONS
Because this alternative would involve a reduction of 218,086 gsf compared to the proposed project,
Alternative B would result in fewer vehicle trips to the site than the proposed project as well as less
building space that would require water and energy use. This alternative would marginally reduce the
already less- than - significant GHG emissions impacts identified under the proposed project. BAAQMD-
recommended construction GHG reduction measures would continue to apply to Alternative B and would
be implemented to further reduce impacts. As with the proposed project, Alternative B would not
contribute considerably to significant cumulative GHG emissions impacts.
HYDROLOGY AND WATER QUALITY
Because Alternative B would involve a similar development footprint and excavation program as the
proposed project, impacts on hydrology and water quality during the construction period would remain
largely the same. Water quality effects of construction activities and groundwater dewatering would
remain less- than - significant under Alternative B through compliance with applicable regulatory
requirements including the Construction General Stormwater Permit.
As with the proposed project, Alternative B would not place structures within a future 100 -year flood
zone that would impede or redirect flood flows, and would not expose people or structures to a significant
risk or loss, injury, or death involving flooding or inundation by seiche, tsunami or mudflow, and these
impacts would remain less than significant. As with the proposed project, Alternative B would not alter
drainage in a manner which would result in substantial erosion or flooding, runoff water would not
exceed the capacity of existing stormwater drainage systems, and no additional sources of polluted runoff
would be created; these impacts would remain less than significant. As with the proposed project, the
Alternative B site plan would include low- impact development infrastructure that would ensure that peak
post - development operational stormwater flows would not exceed the pre - development peak stormwater
flow. As with the proposed project, cumulative development would not cause significant cumulative
hydrology and water quality impacts.
201 Haskins Way Project Draft EIR 5.17 October 12, 2018
5. Alternatives
LAND USE AND PLANNING
Unlike the proposed project, Alternative B would not involve a rezoning of the parcels on the project site.
Instead, the project site would remain zoned as Business Commercial on one parcel (APN 015- 102 -250),
and as Mixed Industrial on the remaining seven parcels (APNs 015- 102 -230, 015 -102 -210, 015 -102 -220,
015 -102 -180, 015- 102 -160, 015- 102 -240, and 015- 102 -290). Under existing zoning, parcels would
provide new office /R &D development potential of up to 1.0 FAR for the Business Commercial District,
similar to the proposed BTP use under the proposed project. Under the existing zoning, the Mixed
Industrial district provides a new office /R &D development potential of 0.4 FAR, or up to 0.6 FAR with
development and implementation of a TDM Plan and design and green building standards, subject to
approval of a CUP. As a result, Alternative B would include approximately 424,877 square feet of floor
area, or 459,514 gsf of office /R &D development (see Table 5. 1, Comparison of Characteristics of the
Proposed Project to the Alternatives).
Alternative B, the Reduced Development Alterative, would reduce overall office /R &D development
compared to the proposed project (about 218,086 gsf less than the proposed project overall) in compliance
with existing zoning, but it is assumed for purposes of this analysis that the general site plan and proposed
land uses would be the same as the proposed project.
Because this alternative would not involve rezoning, the proposed project would not require referral to the
Airport Land Use Commission. However, all other City and agency approvals, including a CUP and
TDM Plan approval, would continue to apply. As with the proposed project, under Alterative B, the
project sponsor would be required to comply with Federal Aviation Administration height and airspace
compatibility notification requirements, San Francisco Bay Conservation and Development Commission
consultation, and Climate Action Plan measure review and selection. Alternative B would not conflict
with any applicable land use plan, policy or regulation with jurisdiction over the project adopted for the
purpose of avoiding or mitigating an environmental effect, and this impact would remain less than
significant. As with the proposed project, cumulative development would not cause significant cumulative
land use and planning impacts.
NOISE
Because construction of Alternative B would still require demolition of existing light industrial uses and
construction of new office/R &D buildings, impacts would remain largely similar to those identified for
the proposed project. Because the square- footage of office/R &D uses would be reduced by 218,086 gsf
under Alternative B, it is expected that construction phases would be the same length and activities as the
proposed project, thereby resulting in the same construction- related noise impacts as those described for
the proposed project. These noise impacts would remain less than significant and, to further reduce
impacts, Improvement Measure IM -NO -1, Construction Noise Minimization and Notification, would
continue to apply to Alternative B. Mitigation Measure MM -NO -2, Groundborne Vibration
Minimization and Avoidance would continue to apply to Alternative B and would reduce impacts
associated with groundbome vibration during construction to a less- than - significant level.
201 Haskins Way Project Draft EIR 5.18 October 12, 2018
5. Alternatives
Because of the reduced intensity of development including fewer vehicle trips and less traffic, operational
increases in noise at and in the vicinity of the project site would be marginally less under Alternative B
than under the proposed project. Mitigation Measure MM -NO -3, Mechanical Equipment Noise
Reductions, would continue to apply to Alternative B, and would reduce project -level impacts associated
with operational mechanical equipment noise to a less- than - significant level. As with the proposed
project, MM -NO -3 would reduce the less than cumulatively considerable contribution to significant
cumulative noise impacts.
TRANSPORTATION AND CIRCULATION
Similar to the proposed project, Alternative B would remove existing industrial uses from the site. Since
these industrial uses were active and generating traffic that is included in the base traffic counts from
2016 and 2017, their trips are subtracted from the total project trip generation to determine the net added
vehicle trips for each project phase. Similar to the proposed project, Alternative B would result in new
vehicle trips in the project vicinity, with a reduction of approximately 40 percent of net new vehicle trips
compared to the proposed project.
As shown in Table 5.4: Vehicle Trip Generation — Alternative B, the Phase 1 project under Alternative
B would generate 1,551 net daily vehicle trips, with 157 in the AM peak hour and 182 in the PM peak
hour (as compared to 2,533 net daily vehicle trips, with 258 in the AM peak hour and 298 in the PM peak
hour under the proposed project). Phase 2 of Alternative B would generate an additional 1,176 net daily
vehicle trips, with 102 in the AM peak hour and 132 in the PM peak hour (as compared to 1,913 net daily
vehicle trips, with 178 in the AM peak hour and 219 in the PM peak hour under the proposed project).
Phases 1 and 2 combined at project buildout would add 2,727 net daily vehicle trips, with 259 in the AM
peak hour and 314 in the PM peak hour (as compared to 4,777 net daily vehicle trips, with 436 in the AM
peak hour and 517 in the PM peak hour under the proposed project).
The trip distribution percentages and choices of routes to and from the project site for Alternative B were
assumed to be consistent with the assumptions used for the analysis of the proposed project as shown in
Table 4.9.8: Project Vehicle Trip Distribution, p. 4.9.34. These assumptions are from the City of South
San Francisco traffic model as updated in July 2018. The vehicle trips generated by Alternative B result in
some reduced transportation impacts as compared to the proposed project as detailed in Table 5.5:
Summary of Transportation Impacts for the Proposed Project and Alternative B.
201 Haskins Way Project Draft EIR 5.19 October 12, 2018
Chapter 5. Alternatives
Table 5.4: Vehicle Trip Generation — Alternative B
Land Use
Land Use
Size
Vehicle Trip
Vehicle Trips
(Sq.Ft.)
Generation
Rates per
Daily
AM
PM
KSF
Peak
Peak
AM (PM)
Hour
Hour
PHASE 1 (Est Complete 2021)
Existing Land Use (To Be Removed)
Existing Mixed Industrial (MI)
Industrial
- 24,075
0.62 (0.62)
-118
-15
-15
Proposed Land Use
New Office /R &D under Existing MI District
Office
211,990
0.81 (0.93)
1,669
172
197
with incentive -based FAR density bonus.
Net New Trips (Phase 1)
1,551
157
182
PHASE 2 (Est Complete 2023)
Existing Land Use (To Be Removed)
Existing Mixed Industrial (MI)
Industrial
- 157,995
0.62 (0.62)
-772
-98
-98
Proposed Land Use
New Office /R &D under Existing MI District
Office
247,524
0.81 (0.93)
1,948
200
230
incentive -based FAR density bonus
Net New Trips (Phase 2)
1,176
102
132
Net New Trips (Phases 1 & 2)
2,727
259
314
Proposed Project Net New Trips
4,777
436
517
Alternative B Compared to Proposed Project
57%
59%
61%
Notes: Trip generation rates from City of South San Francisco Traffic Forecast Model
KSF = thousand square feet
Daily vehicle trips estimated by using the ratio between Daily and
PM peak hour trips from ITE Trip
Generation
Manual, 1011 Edition
Source: Kittelson & Associates, Inc. (2018)
201 Haskins Way Project Draft EIR 5.20 October 12, 2018
5. Alternatives
Table 5.5: Summary of Transportation Impacts for the Proposed Project and Alternative B
Impact Threshold Project Phase 1 Project Buildout Alternative B Phase 1 Alternative B Buildout
201 Haskins Way Project Draft EIR 5.21 October 12, 2018
Impact
CEQA
Impact
CEQA
Impact
CEQA
Impact
CEQA
Determination
Determination
Determination
Determination
EXISTING PLUS PROJECT
Intersection LOS
TR -1: Littlefield /E.
LOS D
AM: LOS E
LTS with Mit
AM: LOS F
LTS with Mit
AM: LOS E
LTS with Mit
AM: LOS E
LTS with Mit
Grand
+2%
+10.9 %*
+18.5 %*
+6.5 %*
+11.1%*
TR -2: Allerton /E.
LOS D
PM: +16.0 %*
Su
PM: +27.9 %*
SU
PM: +9.6 %*
Su
PM: +16.7 %*
SU
Grand
+2%
TR -3: Gateway /S.
LOS D
PM: +3.2 %*
LTS with Mit
PM: +5.7 %*
LTS with Mit
PM: +1.9%
LTS
PM: +3.4 %*
LTS with Mit
Airport
+2%
Intersection Queues
TR -4:
+1%
AM: +<l%
LTS
AM: +<l%
LTS
AM: —1%
LTS
AM: +<11%
LTS
Gateway /Oyster
Pt.
TR -5: Gateway /E.
+1%
AM: +6.1 %*
LTS with Mit
AM: +8.8 %*
LTS with Mit
AM: +3.7 %*
LTS with Mit
AM: +5.3 %*
LTS with Mit
Grand
PM: +17.5 %*
PM: +31.7 %*
PM: +10.5 %*
PM: +19.0 %*
TR -6:
+1%
PM: +8,8 %*
LTS with Mit
PM: +15.9 %*
LTS with Mit
PM: +5.3 %*
LTS with Mit
PM: +9.5 %*
LTS with Mit
Airport /Produce
TR -7:
+1%
AM: +15.3 %*
LTS with Mit
PM: +21.2 %*
LTS with Mit
PM: +9.2 %*
LTS with Mit
PM: +12.7 %*
LTS with Mit
Airport /Grand
Freeway Ramps
TR -8: Freeway
Capacity
<1%
LTS
<1%
LTS
<1%
LTS
<1%
LTS
Ramps
+1%
Trip Generation
TR -9: Trip
>100 Trips
>100*
LTS with Mit.
>100*
LTS with Mit.
>100*
LTS with Mit.
>100*
LTS with Mit.
Generation
Freeway Segments
TR -10: Freeway
LOS E
LOS E
LTS
LOS E
LTS
LOS E
LTS
LOS E
LTS
Segments
+1%
201 Haskins Way Project Draft EIR 5.21 October 12, 2018
5. Alternatives
Impact
Threshold
Project Phase 1
Project Buildout
Alternative B Phase 1
Alternative B Buildout
Impact
CEQA
Impact
CEQA
Impact
CEQA
Impact
CEQA
Determination
Determination
Determination
Determination
Other
TR -11: Safety
LTS
LTS
LTS
LTS
TR -12:
LTS
LTS
LTS
LTS
Emergency
Access
TR -13: Transit
Adds
LTS with Mit.
Adds
LTS with Mit.
Adds
LTS with Mit.
Adds
LTS with Mit.
Capacity
passengers*
passengers*
passengers*
passengers*
TR -14: Transit
Adds
LTS with Mit.
Adds
LTS with Mit.
Adds
LTS with Mit.
Adds
LTS with Mit.
Amenities
passengers*
passengers*
passengers*
passengers*
TR -15:
LTS
LTS
LTS
LTS
Bicycle /Pedestrian
TR -16: Vehicle-
LTS
LTS
LTS
LTS
Miles of Travel
CUMULATIVE
Intersection LOS
C -TR -1:
LOS D
LOS F
LTS
LOS F
LTS
LOS F
LTS
LOS F
LTS
Gateway /Oyster
+1%
<1%
<1%
<1%
<1%
Pt.
C -TR -2:
LOS D
LOS F
LTS
LTS
LOS F
LTS
LTS
Airport /Grand
+2%
<2%
<2%
C -TR -3:
LOS D
AM: LOS F
SU
AM: LOS F
LTS
Airport /Grand
+2%
+3.2 %*
+1.9%
C -TR -4:
LOS D
PM: LOS D
LTS
PM: LOS E
SU
PM: LOS D
LTS
PM: LOS E
SU
Dubuque /Grand
+2%
+4.3 %*
+2.6 %*
OC
C -TR -5: E.
LOS D
PM: LOS E
SU
PM: LOS F
SU
PM: LOS E
LTS
PM: LOS E
SU
Grand /Grand OC
+2%
+2.7 %*
+4.6 %*
+1.6%
+2.8 %*
C -TR -6:
LOS D
PM: LOS F
SU
PM: LOS F
SU
PM: LOS F
SU
PM: LOS F
SU
Gateway /E. Grand
+2%
+3.4 %*
+5.9 %*
+2.0 %*
+3.5 %*
201 Haskins Way Project Draft EIR 5.22 October 12, 2018
5. Alternatives
Impact
Threshold
Project Phase 1
Project Buildout
Alternative B Phase 1
Alternative B Buildout
Impact
CEQA
Impact
CEQA
Impact
CEQA
Impact
CEQA
Determination
Determination
Determination
Determination
C -TR -7: Harbor /E.
LOS D
AM: LOS E
SU
AM: LOS F
SU
AM: LOS E
SU
AM: LOS E
SU
Grand
+2%
+4.0 %*
+6.8 %*
+2.4 %*
+4.1 %*
PM: LOS F
PM: LOS F
PM: LOS F
PM: LOS F
+5.1 %*
+8.8%*
+3.1 %*
+5.3%*
C -TR -8:
LOS D
AM: LOS E
SU
AM: LOS F
SU
AM: LOS E
SU
AM: LOS E
SU
Littlefield /E. Grand
+2%
+7.5 %*
+12.8 %*
+4.5 %*
+7.7 %*
C -TR -9:
LOS D
PM: LOS F
SU
PM: LOS F
SU
PM: LOS F
SU
PM: LOS F
SU
Allerton /E. Grand
+2%
+9.0 %*
+15.6%
+5.4 %*
+9.4%
C- TR -10:
LOS D
PM: LOS F
LTS
PM: LOS F
SU
PM: LOS F
LTS
PM: LOS F
LTS
Airport/Produce
+2%
+1.3%
+2.4 %*
+0,8%
+1.4%
C- TR -11:
LOS D
PM: LOS F
LTS
PM: LOS F
SU
PM: LOS F
LTS
PM: LOS F
LTS
Gateway /S.
+2%
+1.7%
+2.9 %*
+1.0%
+1.7%
Airport
C- TR -12: S.
LOS D
AM: LOS F
LTS
AM: LOS F
AM: LOS F
LTS
AM: LOS F
LTS
Airport /US 101
+1%
+0.9%
+1.6 %*
+0.5%
+1.0%
Ramps
js
C- TR -13: S.
LOS D
AM: LOS F
LTS
AM: LOS F
AM: LOS F
LTS
AM: LOS F
LTS
Airport/Utah
+2%
+1.3%
+2.3 %*
+0.8%
+1.4%
Intersection Queues
C- TR -14:
+1%
AM: -1%
LTS
AM: +<I%
LTS
AM: +<1%
LTS
AM: +<11%
LTS
Gateway /Oyster
Pt.
C- TR -15:
+1%
AM: +4.5 %*
SU
AM: +7.8 %*
SU
AM: +2.7 %*
SU
AM: +4.7 %*
S
Airport /Grand
PM: +2.8 %*
PM: +3.9 %*
PM: +1.7 %*
PM: +2.3 %*
C- TR -16:
+1%
AM: +2.6 %*
SU
AM: +3.7 %*
SU
AM: +1.6 %*
SU
AM: +2.2 %*
SU
Gateway /E. Grand
PM: +6.9 %*
PM: +12.5°/x*
PM: +4.1 %*
PM: +7.5 %*
C- TR -17:
+1%
AM: +1.0 %*
SU
AM: +1.5 %*
SU
AM: +0.6%
SU
AM: +0.9%
SU
Airport/Produce
PM: +3.6 %*
PM: +6.6 %*
PM: +2.2 %*
PM: +4.0 %*
C- TR -18: S.
+1%
AM: +1.7 %*
SU
AM: +2.8 %*
SU
AM: +1:0 %*
SU
AM: +1.7 %*
SU
Airport/US 101
Ramps
201 Haskins Way Project Draft EIR
5.23
October 12, 2018
5. Alternatives
Impact
Threshold
Project Phase 1
Project Buildout
Alternative B Phase 1
Alternative B Buildout
Impact CEQA
Impact
CEQA
Impact
CEQA
Impact
CEQA
Determination
Determination
Determination
Determination
Freeway Segments
C- TR -19: US 101
LOS E
PM: LOS F
PM: LOS F
SU
PM: LOS F
PM: LOS F
LTS
N. of Oyster Pt.
+1%
+0.6%
+1.0 %*
+0.4%
+0.6%
NB
LTS
LTS
US 101 N. of
PM: LOS F
PM: LOS F
PM: LOS F
PM: LOS F
1 -380 SB
+0.6%
+1.1 %*
+0.4%
+0.7%
Freeway Ramps
C- TR -20: NB Off-
Capacity
AM: +1.3 %* SU
AM: +2.3 %*
SU
AM: +0.8%
LTS
AM: +1.4 %*
SU
Ramp to S. Airport
+1%
C- TR -21: SIB On-
Capacity
PM: +2.1 %* SU
PM: +3.9 %*
SU
PM: +1.3 %*
SU
PM: +2.3 %*
SU
Ramp from
+1%
Produce
Bolded results = exceeds threshold
* significant impact
Source: Kittelson & Associates, Inc. (2018)
201 Haskins Way Project Draft EIR 5.24 October 12, 2018
5. Alternatives
Existing Plus Project Conditions — Alternative B
The reduction in trips for Alternative B compared to the proposed project would reduce impacts, but
would not eliminate significant impacts on intersection operations and queues under existing plus project
conditions. Therefore, Mitigation Measures MM -TR -1: Add a Northbound Right -Turn Lane at the
Intersection of Littlefield Avenue and East Grand Avenue; MM -TR -3: Widen and Restripe the
Southbound, Eastbound and Westbound Approaches at the Intersection of Gateway Boulevard/South
Airport Boulevard/Mitchell Avenue; MM -TR -5: Adjust Signal Timing at Gateway Boulevard and East
Grand Avenue; MM -TR -6: Adjust Signal Timing at the intersection of Airport Boulevard/San Mateo
Avenue/Produce Avenue; MM -TR -7: Adjust Signal Timing at Airport Boulevard and Grand Avenue;
MM -TR -9: Implement Transportation Demand Management measures listed in San Mateo County
Congestion Management Program Appendix I; MM- TR -13: Expand local shuttle services; and MM -TR-
14: Provide shuttle stop amenities at Phase 2, as described in Section 4.9 of this EIR, would continue to
apply to Alternative B and would reduce impacts to a less- than - significant level.
The reduction in vehicle trips for Alternative B compared to the proposed project would reduce impacts to
operation of the Allerton Avenue and East Grand Avenue intersection. Mitigation Measure TR -2: Add a
Traffic Signal and a Southbound Right -Turn Lane at the Intersection of Allerton Avenue and East Grand
Avenue would continue to apply to Alternative B, but as described in Section 4.9 of this EIR, the
mitigation measure would remove a portion of the Class II bicycle lanes on Allerton Avenue, disrupting
an existing bicycle facility and resulting in a significant impact. To avoid the significant impact of this
mitigation measure, additional right -of -way would need to be acquired to widen the roadway. Acquisition
would require removal of parking spaces associated with adjacent business; these parking spaces could
not be replaced in alternative locations, such that the associated buildings would not be able to be
occupied. The City of South San Francisco has determined that causing businesses to be non - viable due to
lack of parking would reduce the city's tax base, and that funding sources for acquisition of property for
additional right -of -way are unknown and may not be available for the additional turn lane; therefore, the
mitigation measure is considered infeasible, Similar to the proposed project, while the mitigation measure
could reduce the traffic impact to a less- than - significant level, the mitigation measure under Alternative B
remains infeasible. The cumulative impact would remain significant and Alternative B's contribution
would remain cumulatively considerable.
CUMULATIVE CONDITIONS — ALTERNATIVE B
Unlike the proposed project, Alternative B's contribution to Intersection Impacts C -TR -3 for the
intersection of Airport Boulevard and Grand Avenue; C -TR -5 for the intersection of East Grand
Avenue /Grand Avenue Overcrossing (Phase 1 only); C -TR -10 for the intersection of Airport
Boulevard/Produce Avenue /San Mateo Avenue; C -TR -11 for the intersection of Gateway
Boulevard/South Airport Boulevard/Mitchell Avenue; C -TR -12 for the freeway ramp intersection of
South Airport Boulevard and U.S. 101 Northbound Hook Ramps/Wondercolor Lane; and C -TR -13 for the
intersection of South Airport Boulevard and Utah Avenue, as described in Section 4.9 of this EIR, would
not be cumulatively considerable, as the traffic generated by Alternative B (Phase 1 or buildout) would
add less than the threshold of 2 percent of total traffic at the intersections during peak hours when the
201 Haskins Way Project Draft EIR 5.25 October 12, 2018
5. Alternatives
intersections would operate at LOS E or F without the project (or the 1 percent threshold at a freeway
ramp intersection for C- TR -12). Therefore, under Alternative B. no mitigation would be necessary for
these intersections. However, Alternative B's contribution to significant cumulative impacts for C -TR -5
at project buildout would continue to be cumulatively considerable, as further discussed below.
As with the proposed project, Alternative B's contribution to Impact C -TR -4, Impact C -TR -5 (buildout
only), Impact C -TR -6, Impact C -TR -7, Impact C- TR -10, Impact C- TR -13, Impact C- TR -15, Impact C-
TR-16, Impact C- TR -17, and Impact C -TR -18 on the intersection of East Grand Avenue and Grand
Avenue would continue to be cumulatively considerable. Unlike the proposed project, Alternative B's
contribution to Impact C -TR -5 would not be significant under Phase 1. Mitigation Measure MM- C -TR -5:
Add a Second Northbound Left -Turn Lane would no longer apply to Alternative B under Phase 1. As
discussed in Section 4.9, the City is in the process of updating its East of 101 Area Traffic Impact Fee
(TIF) and Capital Improvement Program (CIP). The City is considering including the improvements
contemplated under Mitigation Measures MM- C -TR -4, MM- C -TR -5, MM- C -TR -6, MM- C -TR -7, MM-
C- TR -10, MM- C- TR -13, MM- C- TR -14, MM- C- TR -15, MM- C- TR -16, MM- C- TR -17, and MM -C -TR-
18 in the updated TIF and CIP. The Phase 1 and Phase 2 project sponsors would pay the applicable TIF in
effect at the time building permits are issued. Until TIF and CIP updates are complete, however, the City
does not have a mechanism for funding these mitigation measures. At this time, the City, therefore,
cannot guarantee that these mitigation measures will be implemented. Thus, while the proposed
mitigation measures could reduce the traffic impact to a less - than - significant level, the City has not yet
completed the TIF and CIP updates to include or fund these mitigation measures, so the overall impact
would remain significant. A TDM program would be required to be prepared and implemented pursuant
South San Francisco Municipal Code Chapter 20.400. However, it cannot be guaranteed that the required
TDM program would reduce intersection traffic by the amount necessary to reduce the project's
contribution to a significant cumulative impact to a less- than - cumulatively considerable level. The
impacts would be significant and unavoidable.
Intersection Impact C -TR -8 for the intersection of Littlefield Avenue and East Grand Avenue and C -TR -9
for the intersection of Allerton Avenue and East Grand Avenue as described in Section 4.9 of this EIR,
would be reduced under Alternative B compared to the proposed project, but Alternative B's contribution
to these impacts would remain cumulatively considerable. Mitigation Measure C -TR -8: Add an
Eastbound Through Lane to the Intersection of Littlefield Avenue/East Grand Avenue and C -TR -9: Add a
Westbound Through Lane and a Southbound Right -Turn Lane at the intersection of Allerton Avenue /East
Grand Avenue would continue to apply to Alternative B. Implementation of these mitigation measures
would provide LOS D or better operations; however, the revisions could impact existing bike lanes. This
secondary impact of these mitigation measures would be significant relative to the bicycle and pedestrian
impact criteria. Mitigation of the secondary impact would require the acquisition of additional right -of-
way from adjacent property owners. The acquisition of property would require removal of parking spaces
for properties that do not have alternative locations for replacement parking, such that the associated
buildings would not be able to be occupied. Because the City of South San Francisco has determined that
acquisition of property for the additional right -of -way to widen East Grand Avenue would economically
affect existing businesses that need parking to remain viable, and that funding for the acquisition is not
201 Haskins Way Project Draft EIR 5.26 October 12, 2018
5. Alternatives
assured, these mitigation measures are considered to be infeasible. As with the proposed project, Impacts
C -TR -8 and C -TR -9 would remain significant and unavoidable with mitigation under Alternative B.
Under Alternative B, the degree of trip reduction would be sufficient to reduce traffic levels and reduce
Alternative B's contribution to significant and unavoidable cumulative impacts to two freeway segments
of U.S. 101 in the PM peak hour, northbound north of Oyster Point Boulevard and southbound north of I-
380 as described under Impact C- TR -19. Under Alternative B, these freeway segments would still operate
at unacceptable LOS F in the future, but project vehicle trips under this alternative would add less than 1
percent of total traffic to the segments during the PM peak hour. Therefore, Alternative B's contribution
to Impact C -TR -19 as described in Section 4.9 of this EIR would not be cumulatively considerable under
Alternative B.
Alternative B's contribution at buildout to Freeway Ramp Impact C -TR -20 for the northbound off -ramp
to South Airport would continue to be a cumulatively considerable but unlike the proposed project,
Alternative B's contribution to Impact C -TR -20 would not be cumulatively considerable under Phase 1.
Freeway Ramp Impacts C -TR -20 for the northbound off -ramp to South Airport (at buildout) and C -TR -21
for the Southbound on -ramp from Produce Avenue (at Phase 1 and buildout), as described in Section 4.9
of this EIR, would be reduced under Alternative B compared to the proposed project, but Alternative B's
contribution to these significant cumulative impacts would remain cumulatively considerable. No feasible
mitigation is available under the proposed project or Alternative B. Alternative B's contribution to these
significant cumulative impacts would remain significant and unavoidable.
UTILITIES AND SERVICE SYSTEMS
Because Alternative B would result in development of 218,086 gsf less office/R &D land use and less
occupied building space than the proposed project, Alternative B's use of potable water supplies and
production of wastewater and solid waste would be less than that identified under the proposed project.
This alternative would marginally reduce the already less- than - significant water supply, wastewater, and
solid waste impacts that had been identified under the proposed project. Alternative B would continue to
involve contribution to the City's Sewer System Capacity Study and Improvement Fee; stormwater
design regulations provided by the City and the Regional Water Quality Control Board; and
implementation of water consumption and solid waste reduction measures provided by the City Climate
Action Plan and CALGreen requirements.
As with the proposed project, the Alternative B site plan would include low- impact development
infrastructure that would ensure that peak post - development operational stormwater flows would not
exceed the pre - development peak stormwater flow and impacts to stormwater systems would remain less
than significant. As with the proposed project, cumulative development would not cause significant
cumulative utilities and service systems impacts.
LESS - THAN - SIGNIFICANT IMPACTS
Section 4.11, Less - than - Significant Impacts, concluded that the proposed project would have no impacts
or less- than - significant impacts in the following analysis areas:
201 Haskins Way Project Draft EIR 5.27 October 12, 2018
5. Alternatives
• Aesthetics (all topics)
• Agriculture and Forest Resources (all topics)
• Geology and Soils (all topics)
• Hazards and Hazardous Materials (all topics)
• Mineral Resources (all topics)
• Population and Housing (all topics)
• Public Services (all topics)
• Recreation (all topics)
Alternative B would occupy the same project site footprint as the proposed project and would have a
similar, though less intensive development program overall (459,514 gsf of development under this
alternative compared to 677,600 gsf under the proposed project). As a result, the construction and
operational impacts of Alternative B, the Reduced Development Alternative, for each of the
environmental topics noted above in Section 4.11, Less Than Significant Impacts would be similar to, but
reduced from, those of the proposed project.
5.4 Environmentally Superior Alternative
CEQA Guidelines Section 15126.6(e)(2) requires identification of an environmentally superior alternative
(the alternative that has the fewest significant environmental impacts) from among the other alternatives
evaluated if the proposed project has significant impacts that cannot be mitigated to a less - than - significant
level. If the No Project Alternative is found to be the environmentally superior alternative, the EIR must
identify an environmentally superior alternative among the other alternatives.
The No Project Alternative would not result in any change to existing environmental conditions.
Alternative B, the Reduced Development Alternative, would result in an overall reduction of impacts
identified for the proposed project. Alternative B would have less square footage (by 218,086 square feet,
or 32 percent less) of office /R &D land use than the proposed project. As such, it would result in lower
trip generation than the proposed project and reduced impacts related to transportation and circulation.
The one project -level impact under the proposed project would remain significant and unavoidable under
Alternative B. The proposed project's contribution to 12 significant cumulative traffic impacts would
remain cumulatively considerable under Alternative B and these impacts would remain significant and
unavoidable. However, due to the reduced number of vehicle trips, Alternative B's contribution to eight
significant cumulative impacts, which would be cumulatively considerable under the proposed project,
would be less than cumulatively considerable under Alternative B. A detailed discussion of the traffic
impact analysis and applicable mitigation measures for Alternative B, the Reduced Development
Alternative, is provided in Section 5.3 under "Transportation and Circulation ".
201 Haskins Way Project Draft EIR 5.28 October 12, 2018
5. Alternatives
5.5 Alternatives Considered but Rejected
Section 15126.6(c) of the CEQA Guidelines provides that an EIR should "identify any alternatives that
were considered by the lead agency but rejected as infeasible during the scoping process and briefly
explain the reasons underlying the lead agency's determination." The screening process for identifying
viable EIR alternatives included consideration of the following criteria: ability to meet the project
objectives; potential ability to substantially lessen or avoid environmental effects associated with the
proposed project; and potential feasibility. The discussion below describes alternatives that were
considered in the preparation and scoping of the EIR, and provides the reasons for eliminating these
alternatives from detailed consideration in the EIR.
5.5.1 Off -Site Alternative
An off -site alternative was eliminated from consideration as an alternative to the proposed project. Due to
the limited primary road network of the East of 101 Area, construction of any similarly sized new
office /R &D uses on land located elsewhere in the East of 101 Area would result in similar project -level
impacts and cumulatively considerable contributions to significant cumulative transportation and traffic
impacts. An off -site alternative in other areas in South San Francisco would not further the City's policies
of developing the East of 101 Area with new opportunities for biotechnology and office/R &D uses and
would not achieve the City's goals in the East of 101 Area. Therefore, an off -site alternative was
considered and rejected.
5.5.2 Revised Design Alternative
An alternative design option was considered and rejected because configuration or changes to the site
plan or architectural design would not reduce transportation and traffic impacts. Therefore, a revised
design alternative was considered and rejected.
5.5.3 Further Reduced Density Alternative
A further reduced density alternative was considered for the purposes of eliminating additional significant
and unavoidable impacts as compared to Alternative B. Reducing the scale of the development to a level
that would eliminate project -level impacts and cumulatively considerable contributions to significant
cumulative traffic impacts would not result in a feasible project. Reducing the amount of development
below allowable FAR would effectively downzone the property and would not be practical. Therefore, a
further reduced density alternative was considered and rejected.
5.5.4 Alternative Land Use
An alternative land use, such as residential or retail, that may result in fewer significant and unavoidable
transportation impacts was also considered and rejected. An alternative land use of industrial would, in
effect, be equivalent to Alternative A, the No Project Alternative. Other alternative land uses (such as
residential or retail) would not be permitted under current City General Plan policies for the East of 101
Area, nor would they be consistent with existing land uses in the vicinity of the project site. Therefore, an
alternative land use development was considered and rejected.
201 Haskins Way Project Draft EIR 5.29 October 12, 2018
5. Alternatives
This page intentionally left blank.
201 Haskins Way Project Draft EIR 5.30 October 12, 2018