HomeMy WebLinkAboutMMRP_101 Gull FEIR.pdf101 Gull Drive Project Mitigation Monitoring and Reporting Program
101 Gull Drive Project - MMRP page 1 of 7
Verification
Mitigation Measure
Timing / Schedule
Implementation
Responsibility
Monitoring Action
Monitoring
Date
Responsibility
Completed
Air Quality
Mitigation Measure Air -1: Basic Construction
Management Practices, Measures: The project
applicant / owner / sponsor shall demonstrate
proposed compliance with all applicable regulations
and operating procedures prior to issuance of
demolition, building or grading permits, including
implementation of the following BAAQMD "Basic
Construction Mitigation Measures".
i) All exposed surfaces (e.g., parking areas, staging
areas, soil piles, graded areas, and unpaved
access roads) shall be watered two times per
day.
ii) All haul trucks transporting soil, sand, or other
p g
Prior to issuance of
Verify requirements are
loose material off-site shall be covered.
construction permits
Applicant / Owner
included in construction
SSF Building
iii) All visible mud or dirt track -out onto adjacent
-and-
/Sponsor
contracts and are met
Division
public roads shall be removed using wet power
During construction
during construction
vacuum street sweepers at least once per day.
The use of dry power sweeping is prohibited.
iv) All vehicle speeds on unpaved roads shall be
limited to 15 mph.
v) All roadways, driveways, and sidewalks to be
paved shall be completed as soon as possible.
Building pads shall be laid as soon as possible
after grading unless seeding or soil binders are
used.
vi) Idling times shall be minimized either by
shutting equipment off when not in use or
reducing the maximum idling time to 5 minutes
101 Gull Drive Project - MMRP page 1 of 7
101 Gull Drive Project - MMRP page 2 of 7
Verification
Mitigation Measure
Timing / Schedule
Implementation
Responsibility
Monitoring Action
Monitoring
Date
Responsibility
Completed
(as required by the California airborne toxics
control measure Title 13, Section 2485 of
California Code of Regulations [CCR]). Clear
signage shall be provided for construction
workers at all access points.
vii) All construction equipment shall be maintained
and properly tuned in accordance with
manufacturer's specifications. All equipment
shall be checked by a certified mechanic and
determined to be running in proper condition
prior to operation.
Post a publicly visible sign with the telephone number
and person to contact at the Lead Agency regarding
dust complaints. This person shall respond and take
corrective action within 48 hours. The Air District's
phone number shall also be visible to ensure
compliance with applicable regulations.
Cultural Resources
Mitigation Measures Cul -1: Cultural Resources
Worker Environmental Awareness Program (WEAP).
The project applicant / owner / sponsor shall retain or
ensure that a qualified archaeologist is retained to
Prior to issuance of
conduct a WEAP training for all construction
construction permits
personnel on the project site prior to construction and
-and-
Verify requirements are
ground -disturbing activities. The training shall include
Applicant /Owner
included in construction
SSF Building
basic information about the types of artifacts that
Prior to grading or
S
/sponsor
contracts and are met
Division
might be encountered during construction activities,
excavation
during construction
and procedures to follow in the event of a discovery.
This training shall be provided for any personnel with
the potential to be involved in activities that could
disturb native soils.
101 Gull Drive Project - MMRP page 2 of 7
101 Gull Drive Project - MMRP page 3 of 7
Verification
Mitigation Measure
Timing / Schedule
Implementation
Responsibility
Monitoring Action
Monitoring
Date
Responsibility
Completed
Mitigation Measures Cul -2: Halt Construction
Activity, Evaluate Find and Implement Mitigation. In
the event that previously unidentified paleontological,
archaeological, historical, or tribal resources are
uncovered during site preparation, excavation or
other construction activity, the project applicant/
Prior to issuance of
Verify requirements are
owner / sponsor shall cease or ensure that all such
building permits
Applicant /Owner
included in construction
SSF Building
activity within 25 feet of the discovery are ceased
-and-
/Sponsor
contracts and are met
Division
until the resources have been evaluated by a qualified
during construction
professional, who shall be retained by the project
During construction
applicant / owner / sponsor, and specific measures
can be implemented by the project applicant / owner
/ sponsor to protect these resources in accordance
with sections 21083.2 and 21084.1 of the California
Public Resources Code.
Mitigation Measures Cul -3: Halt Construction
Activity, Evaluate Remains and Take Appropriate
Action in Coordination with Native American
Heritage Commission. In the event that human
remains are uncovered during site preparation,
excavation or other construction activity, the project
applicant / owner / sponsor shall cease or ensure that
Prior to issuance of
Verify requirements are
all such activity within 25 feet of the discovery are
building permits
Applicant /Owner
included in construction
SSF Building
ceased until the remains have been evaluated by the
-and-
/Sponsor
contracts and are met
Division
County Coroner, which evaluation shall be arranged
during construction
by the project applicant / owner / sponsor, and
During construction
appropriate action taken by the project applicant /
owner / sponsor in coordination with the Native
American Heritage Commission, in accordance with
section 7050.5 of the California Health and Safety
Code or, if the remains are Native American, section
5097.98 of the California Public Resources Code.
101 Gull Drive Project - MMRP page 3 of 7
101 Gull Drive Project - MMRP page 4 of 7
Verification
Mitigation Measure
Timing / Schedule
Implementation
Responsibility
Monitoring Action
Monitoring
Date
Responsibility
Completed
Geology and Soils
Mitigation Measure Geo -1: Compliance with a
design -level Geotechnical Investigation report
prepared by a Registered Geotechnical Engineer and
with Structural Design Plans as prepared by a
Licensed Professional Engineer. The project applicant
Verify geotechnical
/ owner / sponsor shall ensure that proper foundation
Prior to issuance of
Applicant /Owner
recommendations are
SSF Building
g
Division
engineering and construction shall be performed in
building permits
/Sponsor
included in plans and
accordance with the recommendations of a
Registered Geotechnical Engineer and a Licensed
construction contracts
Professional Engineer. The structural engineering
design, with supporting Geotechnical Investigation,
shall incorporate seismic parameters compliant with
the California Building Code.
Hazards and Hazardous Materials
Mitigation Measure Haz-2: Adherence to
Remediation Measures. The project applicant /
owner / sponsor shall ensure that project design and
construction shall incorporate the recommended
remediation measures in an Amended Site Closure
Prior to issuance of
Verify regulatory agency
Plan and Post -Closure Maintenance Plan (PCMP)
building permits
approval of the PCMP
approved by the San Mateo County Department of
-and-
Applicant / Owner
Verify requirements are
SSF Building
Environmental Health, to avoid or reduce the hazards
/Sponsor
included in plans and
Division
related to the presence of hazardous materials (burn
During construction
construction contracts and
ash) and combustible vapor at this site. The
are met during construction
remediation measures are anticipated to include the
following, based on the measures contained in the
current PCMP:
• Placement of cap throughout the development
101 Gull Drive Project - MMRP page 4 of 7
101 Gull Drive Project - MMRP page 5 of 7
Verification
Mitigation Measure
Timing / Schedule
Implementation
Responsibility
Monitoring Action
Monitoring
Date
Responsibility
Completed
area consistent with the final cover / capping plan
in an approved Amended PCMP.
• Installation of building combustible gas protection
and monitoring features to consist of a subfloor
vapor barrier and passive venting system, and
interior alarm system, unless determined not to be
necessary (due to vapor levels following current
removal of landfill materials from nearby portions
of the Oyster Point Landfill).
• Adhering to applicable provisions of the existing
Risk Management Plan and Health and Safety Plan
for soil handling during excavations for utility
trenches, foundations, and other site work.
• Adherence to water conservation standards for
landscaping and irrigation to reduce or eliminate
the potential for water infiltration into underlying
contaminated soil layers.
Transportation
Mitigation Measure TR -2: First- and Last -Mile
Strategies. The project applicant / owner / sponsor
shall coordinate with the City for the project applicant
/ owner / sponsor shall to implement the following
off-site improvements to support the project's first-
Prior to issuance of
Confirm payment of fair
and last -mile and active transportation connections
p
Certificate of
Applicant / Owner
share contribution or
SSF Public Works
necessary to support reductions in Home -Based Work
Occupancy
/Sponsor
coordinate to implement
Department
Vehicle Miles Traveled.
• Participation in first -/last -mile shuttle program(s)
to Caltrain and BART. Shuttles may be operated by
Commute.org and/or other East of 101 shuttle
101 Gull Drive Project - MMRP page 5 of 7
Mitigation Measure
Timing / Schedule
Implementation
Responsibility
Verification
Monitoring
Date
Monitoring Action
Responsibility
Completed
providers offering services open to the general
public.
• Restriping of five crosswalks at the intersection of
Oyster Point Boulevard and Eccles Avenue, one
crosswalk at the intersection of Oyster Point
Boulevard, and two crosswalks at the intersection
of Oyster Point Boulevard and the 329-333 Oyster
Point Boulevard driveway with high -visibility
longitudinal markings to enhance pedestrian
access to the westbound shuttle stop and nearby
land uses.
The project applicant / owner / sponsor shall
additionally coordinate with the City for the project
sponsor to pay fair -share contribution toward the
following off-site improvements to support the
project's first- and last -mile and active transportation
connections necessary to support reductions in
Home -Based Work Vehicle Miles Traveled.
• Modification of the existing eastbound shuttle stop
at the far side of the Oyster Point Boulevard/Eccles
Avenue intersection to provide an accessible five-
foot long by eight -foot -wide landing pad and
pavement markings (if such facilities are not
already fully funded or constructed by the City or
SamTrans).
• Installation of a westbound shuttle stop at the far
side of the Oyster Point Boulevard/Eccles Avenue
intersection including a pole, accessible five-foot
long by eight -foot -wide landing pad, pavement
markings, and shelter (if such facilities are not
already fully funded or constructed by the City or
SamTrans).
101 Gull Drive Project - MMRP page 6 of 7
101 Gull Drive Project - MMRP page 7 of 7
Verification
Mitigation Measure
Timing / Schedule
Implementation
Responsibility
Monitoring Action
Monitoring
Date
Responsibility
Completed
• Provision of eastbound and westbound Class II
buffered bicycle lanes along Eccles Avenue
between Forbes Boulevard and Oyster Point
Boulevard, spanning approximately 3,000 linear
feet. The improvement consists primarily of
restriping the curbside vehicle travel lane in each
direction to a Class II buffered bicycle lane and
signage. The bicycle facility will help close a gap
between the project and a planned Class I shared -
use pathway between Forbes Boulevard / Eccles
Avenue and the South San Francisco Caltrain
station.
Utilities and Services
Mitigation Measure Util-1: Oyster Point Subtrunk
Replacement. An approximately 700 -foot segment of
8 -inch diameter sewer trunk from Eccles Avenue to
Gull Road needs to be upsized to a 12 -inch diameter
Prior to issuance of
Confirm payment of fair
trunk sewer. This segment of sewer trunk is not
Certificate of
Applicant / Owner
share contribution or
SSF Public Works
included in the Sewer Master Plan. The applicant /
Occupancy
/Sponsor
coordinate to implement
Department
owner / sponsor shall either work with the City to
include this improvement in a Sewer Master Plan
update or directly fund their fair share of the
improvement.
101 Gull Drive Project - MMRP page 7 of 7