HomeMy WebLinkAbout2006-12-21 e-packet
~'t\l s::w
B
(0 (')
>- ....
~ ~
v 0
C' :-.~
:4lIFOp..~
-
SPECIAL MEETING
CITY COUNCIL
OF THE
CITY OF SOUTH SAN FRANCISCO
P.O. Box 711 (City Hall, 400 Grand Avenue)
South San Francisco, California 94083
Meeting to be held at:
MUNICIPAL SERVICES BUILDING
CITY COUNCIL COMMUNITY ROOM
33 ARROYO DRIVE
THURSDAY, DECEMBER 21,2006
7:00 P.M.
NOTICE IS HEREBY GIVEN, pursuant to Section 54956 of the Government Code of the
State of California, the City Council of the City of South San Francisco will hold a Special Meeting
on Thursday, the 21 51 day of December, 2006, at 7:00 p.m., in the Municipal Services Building,
Community Room, 33 Arroyo Drive, South San Francisco, California.
Purpose of the meeting:
1. Call to Order
2. Roll Call
3. Public Comments - comments are limited to items on the Special Meeting
Agenda
4. Study Session
a. Water Transit Authority Update
b. Orange Memorial Park recreation building project bid results and
construction options
5. Motion to declare Housing Authority Commissioner Jim Lineberger's
position vacant due to change of residency
6.
Adjournment
~7f2
Cit;-&--
WATER TRANSIT AUTHORITY
~llI!ol!.
J:!~:Jll~ .""",."-n ~-.Ai~f~Li~.~
-
..""...
~
~
~
~
~
WTA
AGENDA ITEM # 4 a
MEMORANDUM
TO:
Barry Nagel
FROM:
Steve Castleberry
DATE:
12/11/2006
RE:
South San Francisco Ferry Service
Barry - per your request, following is a status report on the SSF Ferry project for
update to the Council.
The WT A Board of Directors certified the environmental document for the project
earlier this month. The certification of that document is a major milestone and its
completion is a precursor to final design, permitting, and construction. The
environmental document clears the location of the ferry terminal in the Oyster
Point Marina.
The environmental review and conceptual design work to date has focused solely
on the Oyster Point marina location. In Fall 2005, our design firm, Roma Design,
looked at a number of configurations within the marina and developed one that
had the least impact to the existing marina facilities. The final configuration
requires the removal of two of the existing boat docks (Docks 9 and 10) as
shown in Attachment A. Since January 2006, we have been discussing with the
City and the Harbor District the impact and cost of removal of those two docks.
Negotiations with the Harbor District have centered on the effect that ferry
service will have on the marina operations. The Harbor District requested
payment for a number of mitigations. In August, the Harbor District clarified their
request, which is for approximately $3,770,000 to support the following items:
Q
:::t..
f~i
L&
~9
~~~
1."'"'1
,;;.;:j
(;',':1
!11L6d:
r:~:]
MEMORANDUM
Page 2
Element Cost to be Responsibility Other Terms
paid by for Cost
WTA Increases
Breakwater $450,000 WTA WTA would reimburse the
design Harbor District for actual costs
billed by COE.
Breakwater $550,000 WT A (20% of WTA would pay local match
construction to construction based on invoices from COE.
$750,000 costs)
Docks 9 and 10 $250,000 WTA This work would be included in
dock and gate the construction contract for the
demolition ferry terminal.
West basin $340,000 Harbor This payment would be made at
dredging (from District the completion of the dredging
6' to 8') project.
Reconfiguration $1,380,000 Harbor WT A would make this payment
of Dock 11 District at a date agreed by both parties,
sometime in the Spring of 2007.
Additional Loss $600,000 Harbor Payment would be contingent
of Revenue District on putting 10 vessel berths
between the float and the
shoreline.
Of these items, $250,000 for Docks 9 and 10 has already been factored into the
cost of building the terminal, leaving a net increase in expense related to this
mitigation of approximately $3,520,000.
By September of this year, we were unable to balance the project and mitigation
costs with the budget, and therefore considered an alternative location for this
project. The new site considered is commonly referred to as "The Slot" and is
located about a half mile northwest of the Oyster Point Marina site (see
Attachment B). The slot was formerly used by US Steel to build ships. The site
was initially thought to be too contaminated to be a possible location for the ferry
terminal. Subsequent discussions with resource agencies indicated that impacts
from the ferry to the capped contamination might be minimal and could be
mitigated.
While the site held some promise, the site is controlled through a covenant to US
Steel, who is the "responsible party" for contamination at the site. They have
spent several million dollars remediating the site. While we believed careful
engineering could eliminate the possibility of disturbing capped contaminants in
the area, US Steel believed the risk was too great and rejected our proposal to
locate a ferry terminal site at that location.
120 Broadway, San Francisco, CA 94111 415-291-3377 (F) 415-291-3388
MEMORANDUM
Page 3
In October, we revisited the current project costs, including the Harbor District
request, and project funds available to date.
SSF Construction Costs
. CostltelTl
Environmental and Design
Vessels
Terminal
Waterside
Landside
Harbor District Request
Total Cost
Cost
$3,400,000
$17,000,000
$22,700,000
$3,800,000
$3,520,000
$50,420,000
Funds Available for SSF
RM 2 General
RM 2 - SSF Specific
Federal Earmarks - SSF
Vessels
Federal Earmarks - SSF
Terminal
San Mateo Measure A
Total Funding
$2,204,800
$3,961,900
$19,000,000
$40,566,700
These tables show that the estimated project costs exceed funds available by
approximately $10 million.
The WT A has investigated several ideas that could close the funding gap as
described below.
Idea
Potential New Funds/
Cost SavinQs
$5 million additional
project funds
1. The WT A could contribute an additional $5 million
to the project from our $10 million Federal
allocation ($2.5 million annual allocation over 4
years). This money was originally anticipated for
use for the Berkeley service.
2. Major landside improvements could be deferred
until the City pursues redevelopment of the site.
At that time, the City could include landside
improvements in their redevelopment project.
Up to $2.4 million cost
savings
120 Broadway, San Francisco, CA 94111 415-291-3377 (F) 415-291-3388
MEMORANDUM
Page 4
3. WT A could investigate deferring or omitting the
breakwater improvements. WT A's maritime staff
have investigated the current configuration and
believe the breakwater opening is currently
adequate to provide ferry service.
Up to $1.2 million cost
savings
4. WTA could continue to evaluate vessels
specifications and areas to reduce costs.
Up to $1 million cost
savings
In November, WTA, Harbor District, and City staff met again to discuss the
deferral of improvements (ideas 2 and 3 above). The Harbor District agreed that
deferring the landside improvements might be prudent given that future
redevelopment of the site could require removal of improvements built as part of
this project. However, the Harbor District would like to continue to pursue the
breakwater improvements, leaving a budget deficit (if all the other ideas were
successfully pursued) of $1 million.
At the December 21,2006 Council meeting, I will review the current project
configuration and the implications of changes to the project scope.
***END***
120 Broadway, San Francisco, CA 94111 415-291-3377 (F) 415-291-3388
MEMORANDUM
Page 5
Attachment A
DRAFT
PRELIMINARY SITE DESIGN CONCEPT
_.::~.:::::m:_
o 501 IDol l;<.Or,
South San Francisco Ferry Terminal - Oyster Point Marina
Prtpar,',IJor t}" Sail Fru.'J(i.~", &)' IJn:a r-Vuur Tran.fit .Aut&'ri~)' by ROMA Dwgll Croup 111 ass.viari..'If with Mc1f.1lt (_ Nidx,!
120 Broadway, San Francisco, CA 94111 415-291-3377 (F) 415-291-3388
MEMORANDUM
Page 6
Attachment B
120 Broadway, San Francisco, CA 94111 415-291-3377 (F) 415-291-3388
1
Costs and Funding
Cost ~em
Envlronmentel and Design
Vessels
Terminll
W."'Rllde
l.andslde
Harbor Dislrict
T Olal eost
Source
RM 2 General
RM 2 SSF Specific
FedeRlI Earmarks - SSF V....1s
Federal Earmark "';SSF Terminal
SIIn Mateo-,M..sureA
Total Funding
Amount
$3,400,000
$17,000,000
522,700,000
$3,800,000
>>,520,000
$50,420,000
Amount
. $3,400,000
$12,000,000
$2,204,800
. >>,981,900
$19.000,000
540,588,700
2
Costs and Funding
Cost "em
Environmental and Design
Vessels
Terminal
Wlter1llde
Landllde
HlrborD!ltri<:t
Totel eost
Source
RM 2 General
RM 2 SSF Specific
Federal Elnnsrko - SSF
San
Costs and Funding
Cost Item
Environmental and Design
Vessels
Terminal
Waterside
Landslde
Harbor District
Next steps:
Costs and Funding
Cost Item
Environmental and Design
Vessels
Terminal
Wlterslde
Landslde
Harbor District
Amount
$3,400,000
$17,000,000
Costs and Funding
Cost "em
Environmental and Design
Vessels
Terminal
Waterside
Landside
Harbor District
Total Cost
Source
RM 2 General
RM 2 SSF Specific
Federal Eannlrks - SSF. Vell.is
Federal Elnnart< - SSF Terminal
San MltaoMelSure A
TotelFundlllg
3
-
~'t\\ s!lN
S
~ . ~\.j.\
(0 n
l>-< C;; I
t:l ~
v 0
C41~~~ Stuff ReQort
AGENDA ITEM # 4 h
DATE:
December 21, 2006
TO:
Honorable Mayor and City Council
FROM:
Sharon Ranals, Recreation and Community Services Director
SUBJECT:
Orange Memorial Park Recreation Building Project No. PB-05-1
Study Session Review of Bids Received for Group B and Construction Options
RECOMMENDATION:
It is recommended that the City Council be apprised of the bids received on November 9, 2006 for
the Orange Memorial Park Recreation Building Project, Bid Group B, which were approximately
$2 million higher than the engineer's construction estimate. The Orange Memorial Park
Recreation Building Sub-Committee, comprised of Councilmembers Matsumoto and Fernekes,
and Parks and Recreation Commissioners Bush and Greenwald, have held several meetings with
staff and project consultants to consider options that might yield more favorable results for the
project. They are scheduled to meet again on December 19, 2006 with the goal of reaching
consensus in making a recommendation to the City Council study session on December 21, 2006.
BACKGROUND:
As the City Council is aware, it was a long-standing goal to replace the antiquated Recreation Building
at Orange Memorial Park, which was not in compliance with the Americans with Disabilities Act, and
was only marginally programmable. Identified in the 1990 Orange Park Master Plan, replacement of the
facility was given a high priority by the Parks and Recreation Commission.
The project remained unfunded until competitive and per capita grants were obtained through
Proposition 40, and required local matching funds became available through park-in-lieu fees from new
residential development. The scope includes replacement of the recreation building, relocation and
fencing of two new basketball courts, a separate restroom building, lighting and site improvements.
Funding in the amount of $4.3 million was approved in the Capital Improvement Program for 2006/07.
Structured as a multi-prime contract arrangement, the city advertised for teams comprised of an
architecture firm partnered with a construction management firm. Mary Wong and Donn Logan
Architects were selected to design the building and site improvements; they were coupled with RGM
Construction Management, contracted to provide cost estimation and constructability review from
Staff Report
Subject: Orange Memorial park Recreation Building Project
December 21, 2006
Page 2
design development through the preparation of construction documents. The construction manager
(CM) is responsible for working with staff and the architects to produce bid packages, conducting job
walks for potential bidders, and coordinating the award of bids. The CM schedules the various trades,
ensures coordination and work flow, evaluates progress against contractor billing statements, monitors
quality and compliance, maintains documentation, and resolves construction issues as they arise.
There were several objectives in selecting a multi-prime approach. The administration fees charged by a
general contractor toward his or her own business profit can be extracted and paid instead to an
independent construction management firm looking out for the city's best interests. The method offers
more flexibility in being able to pick and choose the lowest subcontractor bids. In public work
environments, where the lowest responsible bidder must be awarded the contract, general contractor
bidding can result in "low-ball" bids from companies who are awarded the contract, then engage in
strenuous change-order efforts to increase the profitability of the job at the expense of the quality ofthe
project, and potentially the budget. In the multi-prime structure, it is also easier to terminate and replace
one trade contractor whose performance is unsatisfactory, as opposed to being "stuck" with one
contractor for the entire project when performance becomes an issue.
Following the multi-prime approach, the demolition of the old building and preparation ofthe site were
bid independently. A contract for Package A, which came in below the engineer's estimate, was
awarded in September for $688,900. Preparation of the site is nearly complete; additional site work is
included in this contract to be performed after Package B -the building's construction - was completed.
As listed on the following bid summary, sixteen (16) different trade packages were advertised as
Package B. Clearly the key to getting the best prices in any bidding process is to get as much
competition as possible. Toward that goal, extensive outreach to the various trades was done in an effort
to solicit as many bids as possible. Based on disappointingly low turn-out of potential bidders at the
mandatory pre-bid job walk, the bid date was extended by two weeks and additional job walks were held
in the hopes of getting more bidders. However, on bid day only 28 bids were received for the sixteen
(16) separate bid packages, with no bids received for two packages.
Staff Report
Subject: Orange Memorial park Recreation Building Project
December 21, 2006
Page 3
Orange Memorial Park Recreation Building Project
Engineer's Construction Estimates vs. Low Bids - November 9, 2006
I. BASE BIDS
# Bids Estimated Low Bid
Received Cost
Package A
1. Site Work (Awarded) 4 741,000 688,900
---------------------------------------------------------------------------------------------
Package B
2. Concrete 2 113,000 289,000
3. Masonry 1 220,512 280,044
4. Structural Steel 0 77,280 no bids - insert estimate
5. Carpentry 5 649,785 1,631,430
6. Plumbing 2 103,287 181,000
7. Roofing 2 73,239 131,675
8. HV AC/Sheet Metal 4 153,735 260,061
9. Electrical 1 279,595 345,000
10. Fire Sprinklers 2 30,686 34,000
11. Insulation combined with carpentry
12 Metal Stud/ Gyp Board 0 34,984 no bids - insert estimate
13. Painting 2 47,547 59,000
14. Ceramic Tile 1 ~9,163 33,194
15. Glass/Glazing 1 212,925 475,431
16. Casework combined with carpentry
17. Acoustic Ceiling 1 14,135 39,191
18. Flooring 2 58,118 37,992
19. Kitchen Equipment (install) 1 23.751 107.560
Total (Package B) 2,141,742 4,016,824
Difference from Engineer's Estimate (Base Bids): $1,875,100
II. BID ALTERNATES
Estimated
Cost
Low Bid
1. Trash Enclosure
2. Outdoor Barbeque
3. Lockers/Hallway
4. Operable Partitions
5. Restroom Building
Total (Bid Alternates)
21,420
20,000
6,800
25,000
175.000
248,220
19,071
17,226
6,500
52,000
334.937
429,734
Staff Report
Subject: Orange Memorial park Recreation Building Project
December 21, 2006
Page 4
Difference from Engineer's Estimate (Bid Alternates):
$181,514
Total Estimated Cost Package B and Alternates
Difference from Engineer's Estimate:
2,389,962
4,446,558
$2,056,614
DISCUSSION:
Although several of the trade packages in Group B were at or below the estimated cost (flooring, fire
sprinklers, ceramic tile), most of the trades were extremely high. This outcome resulted in extensive
discussion and analysis on the part of staff and the consultants first as to the cause of the discrepancy
between the estimate and the bids, as well as detailed consideration of every option for addressing the
shortfall. A variety of factors were identified as contributing to the disappointing outcome:
. V olatile bid market resulting from too much work currently on the market for too few
contractors; too few bids were received to yield good competition;
. Global market forces on material costs had a negative impact on the number of bidders who
submitted proposals, and drove up the estimates of those who did submit;
. Timing of the project going out to bid was not favorable, as contractors were busy in the fall with
work delayed from a rainy season earlier in the year;
. Other agencies in the Bay Area reported that the bid climate was not favorable for getting
competitive bids.
Staffhas engaged in several weeks of very critical analysis of methods and strategies that might be
employed to get better prices and move forward with getting the project completed. Factors oftime
(schedule); quality (potential reductions and substitutions in materials); budget (obtain more competitive
bids or increase funds available for the project); legal contract requirements that must be observed; and
potential risks of various alternatives have been creatively and aggressively explored with participation
from staff from engineering, public works, the City Attorney, and recreation, as well as our consultants
in order to articulate several viable options to the Sub-Committee.
Construction Options:
Definitions from current Uniform Cost Accounting Procedures:
$125,000 and up:
$30,000 to $125,000:
Up to $30,000:
Major, formal contract
Minor, informal bidding
Purchase Order, informal bids
Option #1: Re-package the Project for General Contractor
. Rej ect all bids
. Incorporate Value Engineering (VE)
Staff Report
Subject: Orange Memorial park Recreation Building Project
December 21, 2006
Page 5
. Repackage for General Contractor (GC) bidding
. Advertise for GC
. Reduce RGM contract to GC management only; increased cost of GC unknown.
Pros: Simpler structure that protects the city the most from legal challenge; more risk delegated to the
contractor.
Cons: Possible 2-4 month delay in schedule; cost implications unknown, likely costs will be higher; how
good the general contractor is critical to the project, have to work with the one contractor - not easy to
dismiss without affecting the schedule (low-ball contractor/change order potential).
Option #2: Multi-Prime (Re-bid Concrete)
. Continue project with informal Uniform Cost Accounting Procedures
. Reject bid packages: Concrete, Masonry, Carpentry, Plumbing, Roofing, MechanicallHV AC,
Electrical, Painting, Storefront and Glazing, Acoustic Ceiling, Kitchen Equipment
. Hold the following bid packages: Fire Sprinkler, Tile, Flooring
. Incorporate Value Engineering
. Re-bid these packages as maior construction contracts: Concrete, Masonry, Structural Steel,
Carpentry, Plumbing, MechanicallHV AC, Electrical, Storefront and Glazing
. Re-bid these packages as minor construction contracts: Roofing, Metal StudlDrywall, Painting,
Acoustic Ceiling, Kitchen Equipment.
Pros: Less delay than Option 1; Probable cost savings by using multiple prime delivery system; possible
cost saving by using informal procedures of Uniform Cost Accounting act could be significant (better
bid coverage for sub-trades); savings from Value Engineering
Cons: 45 day delay to start; cannot begin the foundation until re-bid concrete - more delay than Option
3; reliance on CM for coordinating contractors; more administrative cost for re-bidding; city assumes
more liability for project, and assumes some risk of claims re: splitting the job to avoid competitive bid
process; to work with Attorney's office to minimize.
Option #3: Multi-Prime (Award Concrete with Change Order)
. Continue proj ect with informal Uniform Cost Accounting Procedures
. Reject bid packages: Masonry, Carpentry, Plumbing, Roofing, MechanicallHV AC, Electrical,
Painting, Storefront, Acoustic Ceiling, Kitchen Equipment
. Hold the following bid packages: Fire Sprinkler, Tile, Flooring
. Negotiate/Award Bid Package: Concrete
. Obtain Council 4/5 approval to use own labor for electrical and plumbing for the slab only;
Informal bids for Structural Steel, Metal Stud/Drywall, Painting, Kitchen Equipment; Use own
labor if bids come in too high
Staff Report
Subject: Orange Memorial park Recreation Building Project
December 21, 2006
Page 6
. Alternatively perform the foundation related electrical and plumbing through PO (below $30K
each)
. Incorporate Value Engineering
. Re-bid these packages as maior construction contracts: Masonry, Carpentry, Plumbing,
MechanicallHV AC, Electrical, Storefront and Glazing
. Re-bid these packages as minor construction contracts: Roofing, Acoustic Ceiling
Pros: Schedule benefit - can begin foundation immediately, several month advantage; probable cost
savings by using multiple prime delivery system, probable cost saving by using informal procedures of
Uniform Cost Accounting procedures; savings from Value Engineering.
Cons: Possibly pay more for foundation work; reliance on CM for coordinating contractors; more
administrative cost for re-bidding; city assumes more liability for project, and assumes some risk of
claims re: splitting the job to avoid competitive bid process; to work with Attorney's office to minimize..
FUNDING:
The project is funded from the following sources:
Grants:
Urban Park Act (competitive)
Per Capita Bond Act
Roberti-Z'Berg
2,340,000
268,000
165,000
Developer Fees:
Residual in Zone IV
Stonegate (16 units @ Hillside)
Fairfield
(2,898.400 total to be paid)
Total project budget:
357,000
419,000
750,000
$4,299,000
As noted above, $2.9 million in park-in-lieu fees will be collected from the Fairfield project, of which
only $750,000 have been earmarked for the Orange Park Recreation Building project. $1.065 million
will be collected in park-in-lieu fees from the SummerHill project, which have been earmarked as a
"match" toward the grant funding that the city has received for Centennial Way. Unless construction
costs for the Linear Park see a dramatic increase beyond the estimated cost (similar to the escalation seen
for the recreation building); there should be sufficient developer fees from these two sources for the
match for both projects.
It should be noted that developer fees from these two projects are to be used only for parks and
recreation amenities in Zone IV - East ofEI Camino. Certainly desirable parks and recreation
improvements and amenities can be identified in Zone IV, such as those being suggested in the Orange
Park Master Plan process just underway, however no cost estimates have been developed. No specific
Staff Report
Subject: Orange Memorial park Recreation Building Project
December 21, 2006
Page 7
projects in Zone IV beyond Centennial Way, which includes the dog park, the Orange Memorial Park
Recreation Building, and the Orange Park Master Plan, have been identified by the Parks and Recreation
Commission.
CONCLUSION:
Staff is recommending Option #2 to the Sub-Committee for their consideration. This option is to
follow-through with the multi-prime approach, using a combination of formal re-bidding for packages
over $125,000, informal bidding for packages under $125,000, and purchase orders for some packages
under $30,000, as allowed under Uniform Cost Accounting Procedures. The recommendation is based
on projections that the bidding climate will be more favorable in January (less so as the year progresses);
the city can hold the favorable bids from November 9,2006 for 120 days; ifbetter prices are obtained on
those packages that are rejected and re-bid in January, all the bids can be awarded at the same time when
a bottom line can be determined without any further commitment of funds; contacts made by the
consultant indicated that some of the key packages, including the concrete package, will get more
bidders the second time around; lessons learned from the first round can be incorporated into the second
round of multi-prime bids to save money, such as eliminating costly mock-ups, and showing some costly
material substitutions as add-alternates so that we can better evaluate their value.
Regardless of the bid method selected, the reality is that to accomplish the project a combination of
strategies and sacrifices will have to be made:
Acknowledge that the delay caused by the need to re-bid all or parts of the project will mean that
the building will not be completed in time for Day in the Park 2007, and not until early 2008;
Identify additional funding, and seek City Council authorization to increase the project budget;
Implement "Value Engineering" to reduce costs, but preserve quality, as much as possible;
Make every possible effort to get better bid coverage to obtain better prices;
In spite of the best efforts, there is no guarantee that a lower project cost can be accomplished;
further evaluation and additional options will need to be explored if this is the case.
Approximately $1.7 million in design, utility connections, and site work has been expended or
encumbered in the project to date, in addition to significant time and effort trying to make the most of
the multi-prime bidding method. The course of action discussed above does not further commit city
funds toward the project, except for the cost ofre-bidding, until further effort is made to maximize the
investment that has already been made.
Staff Report
Subject: Orange Memorial park Recreation Building Project
December 21, 2006
Page 8
,...-.....-,
;: .
'~" (
, VI .
By: ~ Ur- ~./~~...~
Sharon Rana1s
Director of Recreation and
Community Services
AGENDA ITEM # 5
City of South San Francisco
Inter-Office Memorandum
DATE: December 21, 2006
TO: Honorable Mayor and City Council Members
City Clerk Sylvia M. Payne ~ ~
FROM:
SUBJECT: HOUSING AUTHORITY COMMISSIONER JIM LINEBERGER
At the special meeting of November 15, 2006, there was a consensus from Council to postpone the
Housing Authority interview/appointment process for an unspecified period of time in order to
continue the recruitment period for a current commission vacancy. Also at that meeting,
Councilwoman Matsumoto suggested Housing Authority Commissioner Lineberger be appointed
member emeritus as he has been unable to attend commission meetings since March 2006, due to a
serious health problem.
As a follow-up to this direction, contact was made with the Housing Authority and it was confirmed
that Mr. Lineberger is now residing in San Mateo in an assisted living facility and his apartment in
South San Francisco has been vacated. Therefore, it is with regret that the appointment of Mr.
Lineberger as member emeritus can not be considered, that his commission appointment be
terminated as Mr. Lineberger no longer resides in South San Francisco, and that the current
recrui tment process include filling Mr. Lineberger's unexpired term, ending March 31, 2009.
If Council concurs with this request, a motion is required to terminate Mr. Lineberger's appointment
as Housing Authority Commissioner.