A RESOLUTION OF CITY COUNCIL OF THE CITY OF SOUTH SAN
FRANCISCO APPROVING NEGATIVE DECLARATION NO. 98-054,
PUD-98-054, SA-98-054 AND PM-98-054 TO ALLOW
DEVELOPMENT OF A 33-UNIT SINGLE FAMILY RESIDENTIAL
SUBDIVISION, AND ONE SINGLE FAMILY LOT ON A 10-ACRE
PARCEL LOCATED AT THE SOUTHWESTERLY CORNER OF
OAKMONT DRIVE AND WESTBOROUGH BOULEVARD IN THE R-
1-E-P SINGLE FAMILY RESIDENTIAL ZONE DISTRICT
WHEREAS, the South San Francisco Planning Commission held a duly noticed public
hearing on November 18, 1999 and December 16, 1999; and
WHEREAS, the Planning Commission by a 3-2 vote, constituting a majority of the
quorum that voted on this matter, supported a motion to approve all of the elements of the
application including the General Plan Amendment; and
WHEREAS, California Government Code section 65354 provides that a recommendation
for approval [of a general plan amendment] shall be made by the affirmative vote of not less than
a majority of the total membership of the commission; and
WHEREAS, the effect of the vote therefore was to recommend approval of the single
family subdivision portion of the application and to simultaneously fail to recommend approval
of the requested mini-storage facility, which was dependent on the General Plan Amendment;
and
WHEREAS, the Planning Commission recommended approval of a Zoning Ordinance
Amendment and Rezoning and Use Permit to create a new Zone District, C-FZ, Commercial B
Fault Zone District, and to rezone the northerly five acres of the subject Oakmont/Westborough
property due to the unique site constraints existing on the property related to existence of active
earthquake fault traces and allow for mini-storage use. However, since the Planning
Commission failed to recommend approval of the General Plan amendment, the Zoning
Ordinance Amendment, Rezoning and Use Permit for the mini-storage could not be
recommended because a Zoning Ordinance Amendment, Rezone and Use Permit would create
zoning inconsistent with the General Plan; and
WHEREAS, the Planning Commission made findings and recommended that the City
Council approve a 33-unit single family residential subdivision and vesting tentative map with
private streets, including requested exceptions for lot size, setbacks, and driveway apron lengths,
on a vacant 5 acre site located at the westerly terminus of Shannon Drive, near the corner of
Oakmont Drive and Westborough Boulevard; and
WHEREAS, the Planning Commission made findings and recommended that the City
Council approve the Tentative Parcel Map to create three separate parcels from the existing 10
acre parcel; and
WHEREAS, on January 26, 2000, the City Council held a properly noticed public
hearing to consider the recommendations of the Planning Commission and take action on the
requested approvals; and
WHEREAS, on January 26, 2000, the City Council denied a General Plan Amendment,
Zoning Amendment, Rezoning and Use Permit relating to the proposed mini-storage facility on
4.9 acres of the subject property, and continued action on the 33-unit single family subdivision
and. 173 acre single family lot. While the Council was supportive of the residential project, it
was reluctant to approve any portion of the project, particularly the Parcel Map, without having
some assurance as to the disposition of the remaining 4.9 acres (Parcel 1). Consequently,
Council directed staff to work with the applicant to address this issue; and
WHEREAS, the City Council based its decision in part on the evidence in the record that
the remaining 4.9 acres (Parcel) has historically had maintenance problems in potential violation
of the City's nuisance laws.
WHEREAS, staff has been working with the applicant over the past few months to devise
a Development Agreement which would allow the residential portion of the project to proceed as
planned and which would also provide adequate assurance that the remaining property would be
maintained in a fashion acceptable to the City until such time as the applicant might receive
development entitlements for this parcel; and
WHEREAS, staff and the applicant have prepared and recommended a Development
Agreement and recommended it to the City Council for approval by ordinance.
NOW THEREFORE, the City Council of the City of South San Francisco makes the
following findings in approving the request for approval of a 33-unit single family residential
planned unit subdivision with private streets, including requested exceptions for lot size,
setbacks, and driveway apron lengths, and on a vacant 5 acre site located at the westerly terminus
of Shannon Drive, near the corner of Oakmont Drive and Westborough Boulevard. These
findings are based on the entire record, including without limitation, public testimony, staff
reports, materials submitted by the City of South San Francisco Planning Commission,
Site plans, floor plans and elevations dated 7-21-99 prepared by Bassenian Lagoni Architects;
Vesting Tentative Map dated January 12, 1999 (Rev. 3) prepared by Tronoff Engineers;
Landscape Plans dated 8/2/99 prepared by Rose Associates; Initial Study and Mitigated Negative
Declaration No. 98-054; and minutes of the July 20 and September 21, 1999 Design Review
Board meetings:
1. The project is consistent with the General Plan which designates the property for
Low Density Residential use at a maximum density of 8 units per acre. The proposed
project of 33 units on a 5-acre parcel yields a density of 6.6 units per acre.
2. The proposed project is generally consistent with the standards and requirements
of the City's Zoning Ordinance which designates the site for R-1 Single Family
Residential. The project includes requested exceptions for lot size, setbacks and
driveway apron lengths which are warranted based on the following:
3. The site has unique constraints including earthquake fault traces and steep slopes.
4. The Design Review Board found the proposed building and landscape design
proposals exceptional.
5. The project has been creatively developed to work with the steep grades and
geologic constraints on the site, provide a subdivision which is compatible with the
existing single family neighborhood, retain large usable open space areas for recreational
use of homeowners and to work as a buffer between the project and the neighboring
homes along Oakmont Drive, and to optimize view corridors within the development
without blocking any neighboring views.
6. The development will result in an intensity of land utilization on higher than that
permitted or required for similar development in this Zone and Land Use category. The
General Plan and Zoning Ordinance would allow more units than included in the project
request.
7. The site is physically suited for the proposed development. The suitability of the
site for development was analyzed thoroughly in the environmental document prepared
for the project.
8. A Negative Declaration has been prepared for the project in accordance with the
provisions of CEQA. Mitigation measures have been incorporated into the project which
will reduce identified impacts to a less that significant level.
9. The proposal will not be adverse to the public health, safety, or general welfare of
the community, nor unreasonably detrimental to surrounding properties or improvements.
10. Subject to minor modifications, included as conditions of approval, the proposal
complies with the City's Design Guidelines.
NOW THEREFORE, the City Council of the City of South San Francisco makes the
following findings in approving the Vesting Tentative Subdivision Map. These findings are
based on the entire record, including without limitation, public testimony, staff reports, materials
submitted by the City of South San Francisco Planning Commission:
1. Subject to acceptance of the exceptions requested under the Planned Unit
Development permit, the tentative map is consistent with the requirements of the City's
Zoning Ordinance.
2. The tentative map complies with the requirements of the State Map Act and with
the City's Subdivision Ordinance (Title 19).
NOW THEREFORE, the City Council of the City of South San Francisco makes the
following findings in approving the Tentative Parcel Map to create three separate parcels from
the existing 10 acre parcel. These findings are based on based on the entire record, including
without limitation, public testimony, staff reports, materials submitted by the City of South San
Francisco Planning Commission:
1. Subject to approval of the proposed Development Agreement, the tentative parcel
map is consistent with the requirements of the City's Zoning Ordinance.
2. The tentative parcel map complies with the requirements of the State Map Act
and with the City's Subdivision Ordinance (Title 19)
NOW, THEREFORE, BE IT RESOLVED that based upon the above
findings and recitals the City Council of the City of South San Francisco
hereby approves Negative Declaration No. 98-054, PUD-98-054, SA-98-054 and PM-
98-054 subject to the Conditions of Approval contained in Exhibit A.
This resolution shall become effective immediately upon its passage and adoption.
I hereby certify that the foregoing Resolution was regularly introduced and adopted by
the City Council of the City of South San Francisco at a Regular meeting held on the 14th
day of June , 2000 by the following vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
Councilmembers Pedro Gonzalez, Eugene R. Mullin and John R. Penna, Mayor
Pro Tem Joseph A. Fernekes and Mayor Karyl Matsumoto
None.
None.
None.
Cit36;Clerk
C:\My Documents\temp reso dir\mini-storage_reso-cc_ 121 .doc
EXHIBIT A
RESOLUTION 66-2000
Oakmont Vistas Subdivision
CONDITIONS OF APPROVAL
PUD, SA, PM, DA & ND-98-054
(As approved by the City Council on June 14, 2000)
A. Planning Division requirements shall be as follow:
The project shall be completed substantially as indicated on the attached site plans, floor plans and
elevations dated 7-21-99 prepared by Bassenian Lagoni Architects; Vesting Tentative Map dated
January 12, 1999 (Rev. 3) prepared by Tronoff Engineers; Landscape Plans dated 8/2/99 prepared
by Rose Associates, except as otherwise modified by the following conditions:
2. The applicant shall comply with all mitigation measures as outlined in Mitigated Negative
Declaration No. ND-98-054 dated October 1999, prepared by Lamphier & Associates.
3. Minimum 15-foot useable rear yards (<5% slope) shall be provided for all units.
Prior to issuance of a building permit, the applicant shall prepare final landscape and irrigation plans
for review and approval of the Planning Division. The plans shall reflect the recommendations of
the Design Review Board as follow:
a. The 6-foot chain link fence indicated on the plans shall be black vinyl clad.
b. Eliminate the pockets of evergreen screen trees along the southerly property line to open up
views to the wooded area.
5. The applicant shall comply with all Standard Conditions of Approval.
(Planning Division contact: Susy Kalkin (650) 877-8535)
B. Engineering Division requirements shall be as follow:
1. PARCEL MAP
The subdivider shall comply with the requirements of the Engineering Division's "Standard
Conditions for Tentative Parcel Maps", as contained in the Engineering Division's "Standard
Conditions for Subdivisions and Private Developments" booklet, dated January 1998. Copies of
this booklet are available to the subdivider and his consultants at no charge.
b. The subdivider shall pay the Engineering Division's actual costs to retain a civil engineer or
land surveyor to plan check and sign the parcel map as the City's Technical Reviewer.
c. The Parcel Map shall include a note listing all soils reports that have been prepared for the land
enclosed by the map boundary.
Conditions of Approval
PUD, SA, PM, DA & ND-98-054
(As approved by the City Council on June 14, 2000)
Page 2 of 10
do
The Parcel Map shall relinquish vehicle access to Westborough Boulevard along the entire
frontage of the street, from Oakmont Drive to Fleetwood Drive, including the entire curb return
at each intersection.
2. SUBDIVISION MAP/PLANNED UNIT DEVELOPMENT
A. PROJECT STANDARDS
The project standards for garage set-backs shall be: 18 feet between the garage door and the back of
the street curb and 20 feet between the garage door and the back of a pedestrian sidewalk, where
there is a sidewalk located in front of the home. These dimensions should permit the parking of
automobiles on the home's driveway apron, without adversely impacting passing vehicles or
pedestrians.
B. STANDARD CONDITIONS
The Subdivider shall comply with the Engineering Division's "Standard Subdivision and Use
Permit Conditions for Townhouse, Condominium and Apartment Developments with Private
Streets and Utilities", consisting of eight pages. These conditions are contained in the Engineering
Division's "Standard Conditions for Subdivisions and Private Developments" booklet, dated
January 1998. (Copies of this booklet are available at no cost from the Planning and Engineering
Divisions).
C. SPECIAL CONDITIONS
1) Vehicle access rights along the entire Westborough Boulevard frontage of the subdivision
shall be relinquished to the City.
2) The project entry turn-around bulb shall be fully lighted to the standards of the South San
Francisco Police Department.
3)
One empty, one and one-quarter inch, PVC, four conduit duct bank and one additional two
inch, PVC conduit and mid- and end-of-run pull-boxes, shall be installed along the entire
project frontage of Westborough Boulevard, in order to accommodate future
communication services within the City.
4)
In connection with the grading, development, home construction and occupancy of the
Oakmont Vistas subdivision, the subdivider shall prepare and submit for City approval,
three copies of a Storm Water Pollution Prevention Plan (SWPPP) for both construction
and post-construction activities, that will result in the filtering of storm water runoff, so as
to prevent silt and toxic materials from being discharged, transported or blown from the
site and entering the adjacent public or private property or San Francisco Bay.
5) As required by City Ordinance, new storm water pollution control devices and filters shall
be installed within the subdivision drainage system, in order to prevent pollutants deposited
Conditions of Approval
PUD, SA, PM, DA & ND-98-054
(As approved by the City Council on June 14, 2000)
Page 3 of 10
within the project from entering Colma Creek and San Francisco Bay. The storm water
filter devices shall be a "Stormcepter", as manufactured by Hydro Conduit, a CDS unit, as
distributed by Kristar Enterprises, or similar and equal devices that will remove pollutants
from the entire subdivision's storm water or irrigation runoff, at a central location
(individual catch basin filters, such as Fossil Filters, are not acceptable due to their high
maintenance requirements). Plans for these facilities shall be prepared by the applicant's
civil engineering consultant and submitted to the Engineering and Water Quality Control
Divisions for review and approval.
6)
The Subdivider shall reimburse the City for all costs to plan check the subject subdivision
final map, private improvement, grading, drainage and utility plans and related documents,
whether accomplished by City staff or private consultants. The subdivider shall reimburse
the City for plan checking and administrative costs in full, prior to the final map being
submitted for the City Council's approval. The final project grading and drainage
construction plans shall be submitted to the City's Geotechnical Consultant for review as to
compliance with their development recommendations. The City shall also be reimbursed
for the costs of this review and for the costs of our inspection services. All on-site
inspections performed by the City Public Works inspection staff shall be reimbursed
monthly, on a time and materials basis.
7)
The project design shall include the provision for concrete or asphalt pedestrian walkways,
physically separated (by location or elevation) from the project's vehicle roadways, in order
to provide safe pedestrian access to each dwelling unit within the subdivision. The
walkway design and location shall be subject to the review and approval of the Engineering
Division and the Police Department.
8)
Existing sewers and storm drains (which were installed in 1960, when the site was
originally graded) that are proposed to be reused to support this project, shall be inspected
by a television camera survey and pressure tested to insure that the pipes are in good
condition, in proper alignment and grade, have tight joints and are not leaking into the
surrounding soil. The applicant shall make any repairs to, or if needed, shall replace these
facilities, as required by the City Engineer (after a review of the inspection reports) to
accommodate the future use of the existing utilities.
9)
Prior to completing the last phase of the development, the subdivider shall repair and
install a 2" asphalt overlay within the Shannon Drive stub street that provides access to the
project. This work shall be performed at no cost to the City of South San Francisco, in
accordance with State standards and to the satisfaction of the City's Senior Construction
Inspector.
10)
The both the Homeowner's Association's monthly budget and fees and the Common Area
Maintenance Contract, shall include the cost of maintaining sanitary sewers, storm
drainage facilities, sub-drain systems, street and area lighting, earth slopes, storm water
retention basin, retaining walls (including the removal of graffiti) and the cleaning and
maintenance of the storm water filter devices. (These items did not appear to be covered in
Conditions of Approval
PUD, SA, PM, DA & ND-98-054
(As approved by the City Council on June 14, 2000)
Page 4 of 10
the proposed sample budget and maintenance contract submitted with the tentative map
documents.)
II)
Extensive earthquake fault and soil engineering studies have been performed for this
project by the Subdivider's geotechnical engineers, Earth Systems Consultants. These
studies have been reviewed by the City's geotechnical reviewer, Cotton, Shires and
Associates. The Subdivider and his design consultants and contractors shall comply with
all recommendations contained in both these reports and the City's geotechnical reviewer's
response letters. In particular, the subdivider shall insure that all existing subdrains within
the site have been located, repaired and replaced (as necessary), have been connected to the
site's drainage system (so that they do not discharge into adjacent property) and that their
location has been documented on an as-built drawing to be submitted to the City and the
Homeowner's Association for our permanent records. (Amended by City Council, June 14, 2000)
12) The proposed above ground detention basin shall be replaced with a suitable underground
alternative subject to the review and approval of the City Engineer.
D. TEMPORARY AND PERMANENT OCCUPANCY
The subdivider will likely request temporary occupancy of one or more homes to be used as
models. Also, the subdivision's permanent residents will probably want to move into their
homes before heavy construction within the project is complete. Either request could result in
the public and/or residents being impacted in various health and safety ways by the remaining
construction activities.
1)
Prior to receiving a temporary certificate of occupancy for a model home within the
subdivision, the developer shall submit for the City staff's review and approval, a plan that
will address at a minimum, the following items:
a. All construction areas shall be completely fenced off from areas accessible by the
visiting public.
b. All areas subject to public travel shall be paved and provided with adequate street and
area lighting, meeting the Police Department's requirements.
c. A parking, traffic and pedestrian safety plan shall be prepared and implemented to the
satisfaction of the City Engineer.
do
Pavement, curb, gutter and sidewalks shall be provided within the model home
complex area to accommodate visitors to the site.
2)
Prior to receiving permanent occupancy permits for the homes within the subdivision, the
developer shall submit for the City staff's review and approval, and shall implement, a plan
that will address, at a minimum, the following items:
Conditions of Approval
PUD, SA, PM, DA & ND-98-054
(As approved by the City Council on June 14, 2000)
Page 5 of 10
ao
All construction areas shall be completely fenced off from the portion of the site
occupied by the new residents. All streets and sidewalks accessible to the public shall
be clear of all trailers, equipment, materials, debris, and other obstructions, and
cleaned, to the satisfaction of the City Engineer.
b. All street lights within the portion of the subdivision accessible to the public shall be
fully operational.
All traffic signs and pavement markings within the portion of the site accessible by the
public shall be installed in accordance with the approved plans, to the satisfaction of
the City Engineer.
do
All site improvements within areas subject to public access shall be complete in
accordance with the approved subdivision improvement, grading, drainage and utility
plans, to the satisfaction of the City Engineer.
e. All noise generating construction activities shall be limited to the hours of 8 a.m. to 6
p.m., Monday through Friday (excluding holidays).
(Engineering Division Contact: Richard Harmon, (650) 829-6652)
C. Police Department requirements shall be as follow:
1. PLANNED UNIT DEVELOPMENT
a. Site Plan and Subdivision Map
1)
The applicant shall submit a list of proposed street names for the project to be reviewed
and approved by the Police Department prior to filing of the parcel maps. City policy
precludes the use of street names that are duplicates or sound alikes of existing streets or
names of living persons. Street names should be easy to pronounce, contain no
unconventional spelling, and be unconfusing so that the public and the children, in
particular, can handle the names in an emergency situation. The use of E1 Rancho Drive is
permissible.
2) No fire lanes will be approved on site. The roadway system shall be designed so that
roadways are wide enough so fire lanes are not necessary.
b. Municipal Code Compliance
1)
The applicant shall comply with the provisions of Chapter 15.48 of the Municipal Code,
"Minimum Building Security Standards" Ordinance, revised May 1995. The Police
Department reserves the right to make additional security and safety conditions, if
Conditions of Approval
PUD, SA, PM, DA & ND-98-054
(As approved by the City Council on June 14, 2000)
Page 6 of 10
necessary, upon receipt of detailed/revised building plans.
2)
The applicant shall assure that the requirements and restrictions on construction noise
(including deliveries, equipment warmup and maintenance, etc.) prescribed in chapter 8.32
of the municipal code are not violated by their own personnel or any subcontractors
working on the project.
c. Security and Safety Conditions
1) Security Planting
a)
Landscaping shall of the type and situated in locations to maximize observation while
providing the desired degree of aesthetics. Security planting materials are encouraged
along fence and property lines and under vulnerable windows.
2) Doors
a) All exterior wood doors and doors leading from enclosed garage areas shall be solid
core with a minimum thickness of 1-3/4".
b) Door framing shall comply with section 15.48.060A. l.h.; details can be provided by
the Building Inspector.
c)
Main entrance doors, pedestrian garage exit doors, and doors leading from enclosed
garage areas into single-family dwellings shall be secured with a single-cylinder
deadbolt lock with a minimum throw of one inch.
The locks into the residence shall be so constructed that both deadbolt and
deadlocking latch can be retracted by a single action of the inside door knob.
(Garage exit doors and rear french doors may have a regular deadbolt lock.)
2. Strike plates shall be secured to wooden jambs with at least 2 inch wood screws.
d)
Vision panels in exterior doors or within reach of the inside activating device shall be
of burglary-resistant glazing or equivalent.~ (This includes the fixed garage window
adjacent to the exit door and french door glazing panels within reach of the locking
device.)
e)
Overhead garage doors shall be equipped with automatic openers and shall not have
bottom vents except those doors having double louvered or shielded vents or approved
alternate devices to protect the locking mechanism.
3) Windows
5/16" security laminate, %" polycarbonate or approved security film treatment, minimum.
Conditions of Approval
PUD, SA, PM, DA & ND-98-054
(As approved by the City Council on June 14, 2000)
Page 7 of 10
a) Windows shall be constructed so that when the window is locked, it cannot be lifted
from the frame.
b) The sliding portion of a sliding glass window shall be on the inside track.
c) Window locking devices shall be capable of withstanding a force of 300 lbs. in any
direction.
4) Numbering
a)
A street number shall be displayed in a prominent location on the street side of the
residence in such a position that the number is easily visible to approaching emergency
vehicles.
1. The numerals shall be no less than four (4) inches in height and shall be of a
contrasting color to the background to which they are attached.
2. The numerals shall be lighted at night.
b) The applicant shall submit a project addressing prior to building permit application.
Addresses should run in a clockwise direction.
5) Lighting
Each entry and exit door shall be equipped with a light source of sufficient wattage to
illuminate the door, porch, and stairway. Area lights, switch controlled from inside the
residence, are encouraged to illuminate the rear and side yards.
6) Other
a)
The developer/applicant shall enclose the entire perimeter of the project with a chain
link fence with necessary construction gates to be locked after normal construction
hours. A security person shall be provided to patrol the project after normal working
hours during all phases of construction, and adequate security lighting shall be
provided to illuminate vulnerable equipment and materials.
b) The applicant's voluntary installation of security alarm systems as a standard amenity
in all residential units constructed, is encouraged on this project.
c)
The applicant shall submit an addressing plan for the project to be reviewed and
approved by the Police Department. The applicant shall indicate if the plan should be
approved considering principles of Feng Shui.
d) The applicant shall submit a phasing plan for the project to be approved by the city as
Conditions of Approval
PUD, SA, PM, DA & ND-98-054
(As approved by the City Council on June 14, 2000)
Page 8 of 10
part of their first building permit application. The phasing plan shall include detail on
the separation of construction activity from the use circulation and occupancy of
residential units and model units and sales office activities.
(Police Dept. Contact: Sgt. Mike Massoni (650) 877-8927)
Do
Fire Prevention requirements shall be as follow:
Fire Flow and Fire Hydrants shall be provided in accordance with Uniform Fire Code Appendices
mA and lll[l. Current information is insufficient to determine at this time. Types of construction
per UBC and square footages are necessary to make a proper determination. Additionally, Fire
Hydrants shall be spaced no further than 300 feet apart.
2. Minimum turning radius for fire equipment is 34' inside radius and 42' outside radius, with a 20'
clear width.
(Contact: Rocque Yballa, Asst. Fire Marshal (650) 829-6670)
E. Building Division requirements shall be as follow:
1. The design and construction of all site alterations shall comply with all applicable codes and
regulations in effect at the time of plan submittal and building permit issuance.
A separate building permit application shall be submitted for each independent structure proposed on
the site. Applications shall be accompanied by five (5) complete sets of construction drawings to
include:
a. Architectural plans
a. Structural plans
b. Electrical plans
c. Plumbing plans
d. Mechanical plans
e. Fire sprinkler plans
f. Landscape/irrigation plans
g. Site/civil plans
h. Structural Calculations
i. Truss Calculations
j. Soils reports
k. Title 24 energy documentation
3. The occupancy classification, construction type and square footage of each building shall be specified
on the plans in addition to justification calculations for the allowable area of each building.
Conditions of Approval
PUD, SA, PM, DA & ND-98-054
(As approved by the City Council on June 14, 2000)
Page 9 of 10
Any demolition of existing structures will require a permit. Submittal shall include three (3) copies of
the site plan, asbestos certification and PG&E disconnect notices. Also, application must be made to
the Bay Area Air Quality Management District prior to obtaining the permit and beginning work.
o
If on-site streets are privately owned, certain on-site improvements such as retaining walls, street light
standards, and private sewer system will require plan review and permits from the Fire Prevention/
Building Division.
A proposed list of street / court names should be submitted to the Fire Prevention / Building Division
for review and approval once the site plan has preliminary approval. List should include a primary and
alternate choice for each street or court. Final decision for street names will be made by the City.
With regard to any grading or site remediation, soils export, import and placement; provide a detailed
soils report prepared by a qualified engineer to address these procedures. In particular the report
should address the import and placement and compaction of soils at future building pad locations and
should be based on an assumed foundation design. This information should be provided to Building
and Engineering Division for review and comments prior to any such activities taking place. A
grading permit may be required for the above-mentioned work.
8. Prior to building permit issuance for the construction of each building, geotechnical and civil pad
certifications are to be submitted.
9. Structures shall be designed to meet all Uniform Building Code requirements to comply as two-story
structures.
10. A second means of exit is required from the third story of all 3-story dwelling units. This would
require the installation of another set of stairs to serve that floor.
11. Water for landscape irrigation should be separately metered.
12. Wooden retaining walls are not approved for use in SSF. Retaining walls must be concrete or
masonry, crib wall, "Keystone", or an equivalent system.
13. All site signage as well as wall signs require a separate permit and application (excluding address
numbering).
14. Monument sign(s) located at the driveway entrance(s) shall have address numbers posted prominently
on the monument sign.
15.
After approval of the project, and prior to application for building permits, applicant shall submit a
request for addressing along with 10 copies of the site plan to the Fire Prevention/Building Division.
Each building will then be assigned an individual address by the Fire Prevention/Building Division.
Subsequently, applicant, and other appropriate departments will receive copies of the addressing plan.
If applicant has a preferred addressing scheme, it should be included with the original request.
Conditions of Approval
PUD, SA, PM, DA & ND-98-054
(As approved by the City Council on June 14, 2000)
Page 10 of 10
16. Each building shall have address numbers posted in a conspicuous place. Numbers for residential
buildings should be minimum 4" in height and either internally or externally illuminated.
17. School fees will be required. Fees for residential units are computed at $1.50 per square foot of
habitable space.
(Contact: Thomas Ahrens, Asst. Building Official (650) 829-6670)
F. Water Quality Control Department requirements shall be as follow:
1. The applicant shall submit to the Stormwater Coordinator a Stormwater Management Plan along
with an Erosion & Sediment Control Plan for the site.
Prior to issuance of a grading permit the applicant shall submit an Erosion Control Plan for
approval. In addition, Post Construction BMP's such as stormceptors, oil/water separators, fossil
filter, and drain inlet stenciling is required of the project.
3. Water Quality Control will comment further when plans for site drainage are submitted.
(Contact: Ray Honan, Environmental Compliance Coordinator (650) 877-8634)
G. Parks, Recreation & Community Services Department requirements shall be as follow:
1. Prior to issuance of a building permit, the applicant shall pay in-lieu park fees in accordance with