HomeMy WebLinkAboutReso 116-2019 (19-754)City of South San Francisco - P.O. Box 711 (City Hall, 400 Grand Avenue) South San Francisco, CA City Council Resolution: RES 116-2019 File Number: 19-754 Enactment Number: RES 116-2019 RESOLUTION APPROVING THE FIRST AMENDMENT TO THE CONSULTING SERVICES AGREEMENT WITH LOTUS WATER FOR THE ORANGE MEMORIAL STORM WATER CAPTURE PROJECT (SD1801), FOR AN ADDITIONAL $1,500,929 FOR A TOTAL CONTRACT AMOUNT NOT TO EXCEED $2,252,720, AND TO EXTEND THE AGREEMENT FOR AN ADDITIONAL YEAR. WHEREAS, on April 26, 2017, the California Department of Transportation (Caltrans) agreed to fund $9,500,000 to the Orange Memorial Storm Water Capture Project (Original Project) through Cooperative Implementation Agreement No. D43CIASF0001; and WHEREAS, City Council, at its regular meeting on January 24, 2018, approved the selection of Lotus Water of San Francisco, California for the engineering and environmental studies, design, permitting and construction bid document preparation services for the Project; and WHEREAS, the agreement included assumptions which would later need to be revisited once the preferred concept was chosen; and WHEREAS, the preferred concept approved by the City Council and carried forward into design development was very different and significantly more complex from the assumed concept and unanticipated services became necessary through the course of the design development; and WHEREAS, Caltrans and the City are in the process of executing Cooperative Implementation Agreement No. D43CIASF0002 for an additional $6,000,000 in funding for the project; and WHEREAS, the Project Team understands that the additional funding will be used to effectively double the treatment capacity of the Original Project by increasing the capacity of the diversion, pretreatment structures, piping, flow splitter, and infiltration gallery; and WHEREAS, in order to continue to advance the design and incorporate the additional scope resulting from the additional funding for the expanded project, staff is requesting an additional amount of $1,500,929 for a total not to exceed amount of $2,252,720. City of South San Francisco Page 1 File Number: 19-754 Enactment Number: RES 116-2019 NOW THEREFORE BE IT RESOLVED, that the City Council of South San Francisco hereby takes the following actions: 1. Approves the Amendment to the Consulting Services Agreement with Lotus Water, attached hereto and incorporated herein as Exhibit B, extending the term for one year and increasing the not to exceed amount by $1,500,929, for an amended total not to exceed amount of $2,252,720. 2. Authorizes the City Manager to execute the Amendment and to make any revisions, amendments, or modifications, deemed necessary to carry out the intent of this resolution which do not materially alter or increase the City's obligations thereunder, subject to approval as to form by the City Attorney. Exhibits: A. Signed Consulting Services Agreement City of SSF - Lotus SSF B. Draft First Amendment Agreement At a meeting of the Special City Council on 9/25/2019, a motion was made by Richard Garbarino, seconded by Mark Addiego, that this Resolution be approved. The motion passed. Yes: 5 Councilmember Nagales, Mayor Matsumoto, Councilmember Addiego, Councilmember Nicolas, and Vice Mayor Garbarino Attest by ;1�4 j4tAft osa Govea Acosta City of South San Francisco Page 2 Exhibit A Signed Consulting Services Agreement City of SSF - Lotus SSF Exhibit B Draft First Amendment Agreement FIRST AMENDMENT TO THE AGREEMENT BETWEEN THE CITY OF SOUTH SAN FRANCISCO AND LOTUS WATER OF SAN FRANCISCO. THIS FIRST AMENDMENT TO THE CONSULTANT SERVICES AGREEMENT is made at South San Francisco, California, as of September 25, 2019 by and between THE CITY OF SOUTH SAN FRANCISCO (“City”), a municipal corporation, and Lotus Water of San Francisco. (“Consultant”), (sometimes referred together as the “Parties”) who agree as follows: RECITALS A. On January 24, 2018, City and Consultant entered that certain Consultant Services Agreement (“Agreement”) whereby Consultant agreed to provide consulting services described in the Exhibit A of the Agreement. A true and correct copy of the Agreement and its exhibits is attached as Exhibit A. B. City and Consultant now desire to amend the Agreement. NOW, THEREFORE, for and in consideration of the promises and other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, City and Contractor hereby agree as follows: 1. All terms which are defined in the Agreement shall have the same meaning when used in this Amendment, unless specifically provided herein to the contrary. The Scope of work is amended and attached as Exhibit B and Exhibit C . 2. Section 1: Term. The December 31, 2020 end date for the term of services identified in Section 1 of the Agreement is hereby replaced with December 31, 2021. 3.Section 2: Compensation. Section 2 of the Agreement shall be amended such that the City agrees to pay Consultant a sum not to exceed $2,252,720, with the understanding that up to $746,914 has already been paid to Consultant. Consultant agrees this is the City’s total contribution for payment of costs under the Agreement unless additional payments are authorized in accordance with the terms of the Agreement and said terms of payment are mutually agreed to by and between the parties in writing. All other terms, conditions, scope of services, and provisions in the Agreement remain in full force and effect. If there is a conflict between the terms of this Amendment and the Agreement, the terms of the Agreement will control unless specifically modified by this Amendment. [SIGNATURES ON THE FOLLOWING PAGE] DRAFT Dated: CITY OF SOUTH SAN FRANCISCO CONSULTANT By: By: Charles M. Futrell City Manager Approved as to Form: By: City Attorney DRAFT 2 I. Scope of Work and Deliverables The following Scope of Work reflects the additional work tasks that are necessary to deliver the Project but were not included in Exhibit A Scope of Services of the Prime Contract. The updated Scope of Work includes both tasks that were wholly unanticipated in the Prime Contract as well as tasks that were anticipated but require expanded resources due to unanticipated project needs and City requests. The City may want Lotus to oversee the construction management (CM) process on their behalf, including the hiring and oversight of a Resident Engineer and Infrastructure Inspector to be onsite throughout the construction period. That service is included as an optional task in this proposal. Required Additional Tasks • Project Management. The City has requested that Lotus Water assume the External Project Manager role on behalf of the City for the duration of the project (i.e., through construction and closeout), in addition to serving in that role for the Project Team. • Design Development and Construction Documents. The project concept resulting from the Phase I alternatives analysis and approved by City Council to be carried forward into Design Development is significantly more complex than the original infiltration gallery concept presented in the RFP due to the addition of a non-potable water treatment & use system and flow-through treatment. As a result, the same deliverables noted in the Prime Contract require additional design effort. • Water Quality Monitoring Plan. The scope of this plan expanded with the addition of a water treatment and use system. • Construction Support Services. Due to the more complex nature of current project design as compared to the RFP project concept, additional site inspections, submittal reviews and responses to requests for information are anticipated. • Lotus Water and Brown and Caldwell will perform site visits throughout the construction period for contractor coordination and construction inspection. • Educational Placard. An interpretive sign with imagery will be designed for installation at the site as construction is being completed. The placard will illustrate the complete system, which will be largely underground, and explain the project’s multiple benefits to the visiting public. • Subconsultant Services o Brown and Caldwell’s original non-binding estimate for Phase II services did not include any hours for Project Management and Coordination. Such hours have been added to this change order request, o CEQA and Permitting. Two additional environmental studies and one additional permit have become necessary. Additionally, the City requested that the Project Team perform CEQA noticing and Native American consulting on their behalf. o Geotechnical Services. The geotechnical engineer will write a Design Criteria Letter and provide a Geotechnical Plan Review for excavation operations. EXHIBIT B DRAFT 3 o Survey. The Project location has moved since the beginning of Phase I, requiring a topographic and utility survey for a different area of the park. o Trenchless Pipe Expert. As a potential means to protect tree roots, a trenchless pipe expert was brought onboard to evaluate the costs and risks of potentially using trenchless technology to install the diversion pipe to the new project area. o Arborist. Given the new project location and that the diversion pipe will be installed via trenching, an arborist is necessary to develop tree protection specifications and to oversee construction during trenching for the diversion pipe installation. This service also involved tree removal prior to project construction. o Health and Safety Plan (HASP). Wood will prepare a Site Management Plan, which will contain the worker HASP as well as guidance on excavation and soils handling at the impacted southern former greenhouse parcel where the diversion and pretreatment structures are located. o Irrigation Plans. The existing irrigation systems within Orange Memorial Park and Centennial Trail where the source water will be replaced with treated stormwater from the water quality treatment shed will need to be retrofit with signage and materials compliance with regulatory requirements for onsite non-potable water reuse systems from the County Health Department and California Plumbing Code. Optional Additional Task •Construction Management. The Resident Engineer and Infrastructure Inspector would be contracted through and managed by Lotus, and their level of effort assumes approximately 50 cumulative hours per week – 25 hours for the Engineer and 25 hours for the Inspector – over a period of seventy (75) weeks. Specific deliverables are listed below particular tasks. The Fee Proposal in the following section is directly linked to the following proposed Scope of Work and deliverables. Required Phase II Tasks 1.Project Management 1.1 Ongoing Project Management (on behalf of the City) Deliverables: Revised Phase II Scope of Work Weekly Progress Calls Caltrans Coordination and Funding Request for an expanded project C/CAG and Water Board Coordination As-needed memoranda and meetingsDRAFT 4 2. Design Development & Construction Documents 2.1 60% Design Development 2.2 90% Construction Documents, including Irrigation Plan 2.3 100% Construction Documents, including Irrigation Plan Deliverables:  60% Submittal (Plans, Spec, and Costs)  90% Submittal (Plans, Spec, Costs, SWPPP, and Educational Placard)  100% Submittal (Plans, Spec, Costs, SWPPP, and Educational Placard) 3. Monitoring Plans 3.1 Develop Water Quality Monitoring Plan for Treatment & Use System Deliverables:  Water Quality Monitoring Plan 4. Construction Support Services 4.1 Site Visits 4.2 Review Contractor Submittals 4.3 Respond to RFI's Deliverables:  Weekly site visits for half day  Additional contractor submittals reviews  Additional responses to RFI’s 5. Subconsultant Services 5.1 CEQA and Permitting Deliverables:  Extended Phase 1 Archaeological Excavations and Report  Delineation of Wetlands/WoUS and Report  CEQA Noticing (on behalf of the City)  Native American Consultation (on behalf of the City)  Report of Waste Discharge Permitting 5.2 Geotechnical Services Deliverables:  Design Criteria Letter  Geotechnical Plan Review 5.3 Topographic and Utility Survey for New Project Area Deliverables:  Base Map with Boundary, Topography, Trees, Structures, Utilities, etc. 5.4 Trenchless Pipe Evaluation Deliverables: DRAFT 5  Cost Estimation and Risk Evaluation 5.5 Arborist Deliverables:  Tree Removal (4 Eucalyptus and grind stumps below grade)  Tree Protection Specifications  Construction Observation during Pipe Trenching 5.6 Site Management Plan Deliverables:  Worker Health and Safety Plan (HASP) for southern former greenhouse parcel  Soils management guidance for southern former greenhouse parcel Optional Phase II Tasks 6. Construction Management 6.1 Construction Management (on behalf of the City) Deliverables:  Hiring and management of Resident Engineer and Infrastructure Inspector  Administrative Paperwork  Weekly Progress Calls DRAFT 6 II. Fee Proposal Our detailed fee estimate for Phase II is provided in Attachment A, which shows the full fee needed to complete each Phase II task. The summary table below shows each Phase II task in the first two columns and its updated fee total in the third column. The fourth column shows the fee estimate from the Prime Contract, including the 10% contingency that was included for the Fee Estimate in the Prime Contract. The fifth column shows the difference between the updated fee estimates and the fees from the Prime Contract, which is the total fee estimate for the change order request. * The fee for the Construction Management optional task is taken from the two Cooperative Implementation Agreements (CIAs) between Caltrans and the City of South San Francisco; $776,800 is the sum of the budget estimates in the two CIAs for that task. An actual task order with final budget for Construction Management services will be issued prior to construction. Proposals from individual subcontractors are available upon request. III. Schedule The detailed Project schedule is on the following page. Lotus performed a critical path analysis on the schedule provided in the RFP. Slight adjustments were made to dates for some key deliverables (e.g., sequencing the delivery of the 100% Construction Documents, the City Council approval, and the development of the Bid Documents in an achievable time frame). Critical dependencies are reflected in the schedule. Task #Task Description UPDATEDAMOUNTPRIME CONTRACTAMOUNT(with 10% Contingency)CHANGE ORDER REQUEST AMOUNTX Project Management and Coordination 93,843$ 21,137$ 72,707$ XI Design Development. Construction Documents 275,160$ 136,829$ 138,331$ XII Operations & Maintenance Template 14,089$ 14,089$ -$ XIII Monitoring Plans 19,780$ 15,710$ 4,070$ XIV Bidding Services 15,852$ 15,842$ 9.80$ XV Construction Support Services 96,990$ 51,370$ 45,620$ XVI Additional Subconsultant Services 253,946$ -$ 253,946$ 769,660$ 254,977$ 514,682$ XVII Construction Management*776,800$ -$ 776,800$ TOTAL ALL TASKS: 1,546,460$ 254,977$ 1,291,482$ CHANGE ORDER TOTAL REQUIRED TASKS: Orange Memorial Park Stormwater Capture Project No.: sd1801 Phase II - Required Tasks Phase II - Optional TaskDRAFT Orange Memorial Park Water Capture Proejct City of South San Francisco Lotus Water START END WEEKS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 CEQA and Environmental Permitting Task 1 Environmental Evaluation & Documentation 1/2/19 8/28/19 34 Task 2 Archaeological Investigation 2/26/19 4/23/19 8 Task 3 Regulatory Requirements and Permits 5/22/19 12/4/19 28 Design Development, Construction Documents Task 1 Receive updated expanded survey 1/21/19 1/21/19 0.0 Task 2 30% Design Drawings 1/1/19 3/4/19 Task 3 60% Submittal (Plans, Spec, and Costs)3/5/19 6/8/19 14 Task 4 90% Submittal (Plans, Spec, Costs, and SWPPP)7/17/19 10/23/19 14 Task 5 100% Submittal (Plans, Spec, Costs, and SWPPP)11/13/19 1/10/20 8 Operations & Maintenance Template, Monitoring Plans Task 1 Develop O&M Template 8/21/19 10/23/19 9 Task 2 Develop Hydrologic Monitoring Plan 10/28/19 12/23/19 8 Task 3 WQ Monitoring Baseline Development and Plan 10/28/19 12/23/19 8 Bid Process Task 1 Prepare Bid Documents 1/13/20 2/3/20 3 Task 2 Pre-Bid Meeting 2/6/20 2/6/20 0 Task 3 Respond to Inquires 2/6/20 2/20/20 2 Task 4 Prepare Addenda to Bid Documents 2/21/20 3/6/20 2 Task 5 Award 3/20/20 3/20/20 0 Construction Period Task 1 Construction 5/4/20 10/11/21 75 2021 105-144 Jan-OctMay - Dec 2020 AprFebMarAprMay 70-104 Jan MarFeb 2019 June July Aug Sept Oct Nov Dec TASK Project Start:Wed, 1/2/2019 2018 Jan DRAFT DETAILED FEE ESTIMATE DRAFT Prime Consultant: Lotus Water Project Role/Classification, Name Project Manager, Shuana Dunton, PETechnical Lead, Robert Dusenbury, PE Quality Review/Compliance,Eric Zickler, PESenior Project Engineer, Jess Wala, PEProject Engineer, Sarah TeplitskyProject Controls/Contracts, Pam Drake Direct Expenses ($)HoursLabor CostDirect ExpensesTOTAL COSTTechnical Lead, Mike Flake, PE Project Manager, Rosey Jencks, PlannerSenior Engineer, Manjit Saini, PEAmy Neal, PE, Project EngineerProject Engineer, Valerie Fuchs, PE Senior Cost Estimator, Nitesh PoladiaStructural Engineer,Dwight EvansCADD Drafter,Alan SantiagoProject Engineer I, Hamideh Riazi, PE Direct Expenses ($)HoursLabor CostDirect ExpensesTOTAL COSTHoursLabor CostDirect ExpensesTOTAL COSTHoursLabor CostDirect ExpensesTOTAL COSTTask # Billing Rate $195 $195 $195 $165 $140 $95 $291 $254 $254 $166 $133 $185 $185 $130 $111 X Project Management and Coordination 140 232 2 12 20 24 400$ 430 79,990$ 400$ 80,390$ 5 35 12 0 0 0 0 0 0 60$ 52 13,393$ 60$ 13,453$ 0 -$ -$ -$ 482 93,383$ 460$ 93,843$ X.A Confirm Project and Verify/Refine Scope 20 12 2 12 46 8,610$ -$ 8,610$ 1 1 4 6 1,561$ -$ 1,561$ 0 -$ -$ -$ 52 10,171$ -$ 10,171$ X.B On-going Project Management 80 160 24 200$ 264 49,080$ 200$ 49,280$ 30 30 7,620$ -$ 7,620$ 294 56,700$ 200$ 56,900$ X.C Coordination meetings with City staff and outside agencies 40 60 20 200$ 120 22,300$ 200$ 22,500$ 4 4 8 60$ 16 4,212$ 60$ 4,272$ 0 -$ -$ -$ 136 26,512$ 260$ 26,772$ XI Design Development. Construction Documents 262 232 52 56 480 0 1,500$ 1082 182,910$ 1,500$ 184,410$ 22 8 116 0 0 42 76 108 80 250$ 452 82,648$ 250$ 82,898$ 0 -$ -$ -$ 1534 265,558$ 1,750$ 267,308$ XI.A 60% Submittal (PS&E)150 120 24 240 500$ 534 90,930$ 500$ 91,430$ 12 4 80 22 40 60 40 250$ 258 48,538$ 250$ 48,788$ 0 -$ -$ -$ 792 139,468$ 750$ 140,218$ XI.B 90% Submittal (PS&E + SWPPP)64 64 16 32 140 500$ 316 52,960$ 500$ 53,460$ 6 4 20 12 24 32 22 120 21,104$ -$ 21,104$ 0 -$ -$ -$ 436 74,064$ 500$ 74,564$ XI.C 100% Submittal (PS&E + SWPPP)48 48 12 24 100 500$ 232 39,020$ 500$ 39,520$ 4 16 8 12 16 18 74 13,006$ -$ 13,006$ 306 52,026$ 500$ 52,526$ XII O&M Template 12 24 0 0 48 0 -$ 84 13,740$ -$ 13,740$ 0 0 0.5 0 0 0 0 0 2 -$ 2.5 349$ -$ 349$ 0 -$ -$ -$ 87 14,089$ -$ 14,089$ XII.A Develop O&M Template 12 24 48 84 13,740$ -$ 13,740$ 0.5 2 3 349$ -$ 349$ 0 -$ -$ -$ 87 14,089$ -$ 14,089$ XIII Monitoring Plans 0 40 4 0 80 0 -$ 124 19,780$ -$ 19,780$ 0 0 0 0 0 0 0 0 0 -$ 0 -$ -$ -$ 0 -$ -$ -$ 124 19,780$ -$ 19,780$ XIII.A Develop Hydrologic Monitoring Plan 20 2 40 62 9,890$ -$ 9,890$ 0 -$ -$ -$ 0 -$ -$ -$ 62 9,890$ -$ 9,890$ XIII.B Develop Water Quality Monitoring Plan 20 2 40 62 9,890$ -$ 9,890$ 0 -$ -$ -$ 0 -$ -$ -$ 62 9,890$ -$ 9,890$ XIV Bidding Services 24 0 0 0 30 0 -$ 54 8,880$ -$ 8,880$ 0 0 0 42 0 0 0 0 0 -$ 42 6,972$ -$ 6,972$ 0 -$ -$ -$ 96 15,852$ -$ 15,852$ XIV.A Prepare Bid Documents 10 18 28 4,470$ -$ 4,470$ 30 30 4,980$ -$ 4,980$ 0 -$ -$ -$ 58 9,450$ -$ 9,450$ XIV.B Attend Pre-Bid Meeting 6 4 10 1,730$ -$ 1,730$ 4 4 664$ -$ 664$ 0 -$ -$ -$ 14 2,394$ -$ 2,394$ XIV.C Respond to Inquires 4 4 780$ -$ 780$ 0 -$ -$ -$ 0 -$ -$ -$ 4 780$ -$ 780$ XIV.D Prepare Addenda to Bid Documents 8 8 1,120$ -$ 1,120$ 8 8 1,328$ -$ 1,328$ 0 -$ -$ -$ 16 2,448$ -$ 2,448$ XIV.E Attend Bid Opening and Review Bids 4 4 780$ -$ 780$ 0 -$ -$ -$ 0 -$ -$ -$ 4 780$ -$ 780$ XV Construction Support Services 52 126 4 124 156 0 600$ 462 77,790$ 600$ 78,390$ 0 0 0 80 40 0 0 0 0 -$ 120 18,600$ -$ 18,600$ 0 -$ -$ -$ 582 96,390$ 600$ 96,990$ XV.A Attend Onsite Meetings 4 4 8 1,340$ -$ 1,340$ 4 4 664$ -$ 664$ 0 -$ -$ -$ 12 2,004$ -$ 2,004$ XV.B Review Submittals 12 12 48 72 11,400$ -$ 11,400$ 0 -$ -$ -$ 0 -$ -$ -$ 72 11,400$ -$ 11,400$ XV.C Respond to RFI's 12 12 48 72 11,400$ -$ 11,400$ 44 44 7,304$ -$ 7,304$ 0 -$ -$ -$ 116 18,704$ -$ 18,704$ XV.D Prepare Design-Related Change Orders 4 2 10 16 2,570$ -$ 2,570$ 10 10 1,660$ -$ 1,660$ 0 -$ -$ -$ 26 4,230$ -$ 4,230$ XV.E Final Inspection and Punch List 4 6 10 1,620$ -$ 1,620$ 6 6 996$ -$ 996$ 0 -$ -$ -$ 16 2,616$ -$ 2,616$ XV.F Prepare As-Builts 8 4 16 40 68 10,580$ -$ 10,580$ 16 40 56 7,976$ -$ 7,976$ 0 -$ -$ -$ 124 18,556$ -$ 18,556$ XV.G Site Visits (50 Weeks)100 100 600$ 200 36,000$ 600$ 36,600$ 0 -$ -$ -$ 0 -$ -$ -$ 200 36,000$ 600$ 36,600$ XV.H Closeout 8 8 16 2,880$ -$ 2,880$ 0 -$ -$ -$ 0 -$ -$ -$ 16 2,880$ -$ 2,880$ XVI Subconsultant Coordination 46 66 0 0 26 0 -$ 138 25,480$ -$ 25,480$ 0 0 0 0 0 0 0 0 0 -$ 0 -$ -$ -$ 1350.5 222,707$ 13,610$ 236,317$ 1489 248,187$ 13,610$ 261,797$ XVI.A Wood Environmental: CEQA and Permitting 8 40 48 9,360$ -$ 9,360$ 0 -$ -$ -$ 270 44,230$ 8,610$ 52,840$ 318 53,590$ 8,610$ 62,200$ XVI.B Cotton Shires & Associates: Geotechnical Services 4 4 8 1,560$ -$ 1,560$ 0 -$ -$ -$ 40 7,800$ -$ 7,800$ 48 9,360$ -$ 9,360$ XVI.C Siegfried Engineering: Topographic and Utility Survey 4 4 8 1,340$ -$ 1,340$ 0 -$ -$ -$ 480 76,410$ 4,500$ 80,910$ 488 77,750$ 4,500$ 82,250$ XVI.D DMC Consulting: Trenchless Pipe Evaluation 8 4 12 2,120$ -$ 2,120$ 0 -$ -$ -$ 12 2,588$ -$ 2,588$ 24 4,708$ -$ 4,708$ XVI.E Davey Trees: Arborist 8 4 12 2,340$ -$ 2,340$ 0 -$ -$ -$ 200 35,000$ -$ 35,000$ 212 37,340$ -$ 37,340$ XVI.F Wood Environmental: Site Management Plan w/ HASP 4 4 8 1,560$ -$ 1,560$ 0 -$ -$ -$ 68 11,228$ -$ 11,228$ 76 12,788$ -$ 12,788$ XVI.G Sweeney & Associates: Irrigation Plan 8 8 16 32 5,360$ -$ 5,360$ 0 -$ -$ -$ 188 31,600$ -$ 31,600$ 220 36,960$ -$ 36,960$ XVI.H InCommon: Educational Placard Design 2 2 2 6 1,060$ -$ 1,060$ 0 -$ -$ -$ 40 6,000$ 500$ 6,500$ 46 7,060$ 500$ 7,560$ XVI.I Paradigm: Hydrologic Modeling 4 4 780$ -$ 780$ 0 -$ -$ -$ 53 7,852$ -$ 7,852$ 57 8,632$ -$ 8,632$ XVI.J Hollins Consulting: Construction Management (75 weeks)240 240 240 720 116,400$ -$ 116,400$ 0 -$ -$ -$ 3885 660,400$ -$ 660,400$ 4605 776,800$ -$ 776,800$ TOTAL TASKS 536 720 62 192 840 24 2,500$ 2374 408,570$ 2,500$ 411,070$ 27 43 128.5 122 40 42 76 108 82 310$ 668.5 121,962$ 310$ 122,272$ 1350.5 222,707$ 13,610$ 236,317$ 4393 753,239$ 16,420$ $ 769,660 Specialty Subconsultants* Construction Documents Phase Orange Memorial Park Stormwater Capture Project No.: sd1801 Project Lead, Engineering Design, Site Development Engineering, Stormwater Management, Regulatory Support, and Water Capture and Reuse Subconsultant: Brown & Caldwell Engineering Design, Open Channel Engineering, Structural Engineering, Electrical Engineering, and Mechanical Engineering Project Summary * Subconsultant proposals available upon request DRAFT 2 I.Scope of Work and Deliverables The following Scope of Work reflects the work tasks that are necessary to deliver the Expanded Project. An Expanded Project is anticipated to extend the design period by at least six (6) weeks and the construction period by twenty-five (25) weeks. As a result of these longer durations, additional efforts are needed to complete design and construction. Specific deliverables are listed below particular tasks. The Fee Proposal in the following section is directly linked to the following proposed Scope of Work and deliverables. Required Tasks 1.Project Management 1.1 Ongoing Project Management Deliverables: Weekly Progress Calls Caltrans Coordination C/CAG and Water Board Coordination As-needed memoranda and meetings 2.Design Development & Construction Documents 2.1 60% Design Development 2.2 90% Construction Documents 2.3 100% Construction Documents Deliverables: 60% Submittal (Plans, Spec, and Costs) 90% Submittal (Plans, Spec, Costs, and SWPPP) 100% Submittal (Plans, Spec, Costs, and SWPPP) 3.Construction Support Services 3.1 RFI Responses 3.2 Contractor Submittal Reviews 3.3 Design-related Change Orders 3.4 Contractor Coordination and Site Inspections Deliverables: RFI responses Contractor Submittals Reviews Change Orders Site Visits for Contractor Coordination and Construction Inspections EXHIBIT C DRAFT 3 II.Fee Proposal Our detailed fee estimate for the Expanded Project is provided in Attachment A, which shows the fees needed for each Project Team member to complete each task. The summary table below shows each task and its total fee. The optional Construction Management task is broken out separately to show the Expanded Project fee total with and without its inclusion. Proposals from individual subcontractors are available upon request. III.Schedule The detailed Project schedule is on the following page. Construction is anticipated to begin in May 2020. TASK #TASK DESCRIPTION FEE ESTIMATE X Project Management and Coordination 49,590$ XI Design Development. Construction Documents 111,286$ XV Construction Support Services 48,580$ TOTAL ALL TASKS: 209,456$ Orange Memorial Park Stormwater Capture Project No.: sd1801 Required Tasks DRAFT Orange Memorial Park Water Capture Proejct City of South San Francisco Lotus Water START END WEEKS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 CEQA and Environmental Permitting Task 1 Environmental Evaluation & Documentation 1/2/19 8/28/19 34 Task 2 Archaeological Investigation 2/26/19 4/23/19 8 Task 3 Regulatory Requirements and Permits 5/22/19 12/4/19 28 Design Development, Construction Documents Task 1 Receive updated expanded survey 1/21/19 1/21/19 0.0 Task 2 30% Design Drawings 1/1/19 3/4/19 Task 3 60% Submittal (Plans, Spec, and Costs)3/5/19 6/8/19 14 Task 4 90% Submittal (Plans, Spec, Costs, and SWPPP)7/17/19 10/23/19 14 Task 5 100% Submittal (Plans, Spec, Costs, and SWPPP)11/13/19 1/10/20 8 Operations & Maintenance Template, Monitoring Plans Task 1 Develop O&M Template 8/21/19 10/23/19 9 Task 2 Develop Hydrologic Monitoring Plan 10/28/19 12/23/19 8 Task 3 WQ Monitoring Baseline Development and Plan 10/28/19 12/23/19 8 Bid Process Task 1 Prepare Bid Documents 1/13/20 2/3/20 3 Task 2 Pre-Bid Meeting 2/6/20 2/6/20 0 Task 3 Respond to Inquires 2/6/20 2/20/20 2 Task 4 Prepare Addenda to Bid Documents 2/21/20 3/6/20 2 Task 5 Award 3/20/20 3/20/20 0 Construction Period Task 1 Construction 5/4/20 10/11/21 75 2021 105-144 Jan-OctMay - Dec 2020 AprFebMarAprMay 70-104 Jan MarFeb 2019 June July Aug Sept Oct Nov Dec TASK Project Start:Wed, 1/2/2019 2018 Jan DRAFT 4 DETAILED FEE ESTIMATE DRAFT Prime Consultant: Lotus Water Project Role/Classification, Name Project Manager, Shuana Dunton, PETechnical Lead, Robert Dusenbury, PE Quality Review/Compliance,Eric Zickler, PESenior Project Engineer, Jess Wala, PEProject Engineer, Sarah TeplitskyProject Controls/Contracts, Pam Drake Direct Expenses ($)HoursLabor CostDirect ExpensesTOTAL COSTTechnical Lead, Mike Flake, PE Project Manager, Rosey Jencks, PlannerSenior Engineer, Manjit Saini, PEProject Engineer,Hamed Hakimelahi, PESenior Cost Estimator, Nitesh PoladiaStructural Engineer Dwight EvansStructural Engineer Eric FalkenCADD Drafter Alan SantiagoDirect Expenses ($)HoursLabor CostDirect ExpensesTOTAL COSTHoursLabor CostDirect ExpensesTOTAL COSTTask # Billing Rate $195 $195 $195 $165 $140 $95 $291 $254 $254 $150 $185 $185 $254 $130 X Project Management and Coordination 60 60 0 0 0 12 -$ 132 24,540$ -$ 24,540$ 0 75 0 40 0 0 0 0 -$ 115 25,050$ -$ 25,050$ 247 49,590$ -$ 49,590$ X.A On-going Project Management 60 60 12 132 24,540$ -$ 24,540$ 75 40 115 25,050$ -$ 25,050$ 247 49,590$ -$ 49,590$ XI Design Development. Construction Documents 100 100 14 40 200 0 -$ 454 76,330$ -$ 76,330$ 10 0 40 70 8 34 4 20 -$ 186 34,956$ -$ 34,956$ 640 111,286$ -$ 111,286$ XI.B 90% Submittal (Plans, Spec, and Costs)60 60 8 24 120 272 45,720$ -$ 45,720$ 6 24 40 4 20 2 12 108 20,350$ -$ 20,350$ 380 66,070$ -$ 66,070$ XI.C 100% Submittal (Plans, Spec, and Costs)40 40 6 16 80 182 30,610$ -$ 30,610$ 4 16 30 4 14 2 8 78 14,606$ -$ 14,606$ 260 45,216$ -$ 45,216$ XV Construction Support Services 0 50 0 50 0 0 450$ 100 18,000$ 450$ 18,450$ 0 0 80 53 0 0 0 12 300$ 145 29,830$ 300$ 30,130$ 245 47,830$ 750$ 48,580$ XV.C RFIs, Submittals, Design-related Change Orders 0 -$ -$ -$ 55 28 12 95 19,730$ -$ 19,730$ 95 19,730$ -$ 19,730$ XV.G Contractor Coordination and Site Inspections 50 50 450$ 100 18,000$ 450$ 18,450$ 25 25 300$ 50 10,100$ 300$ 10,400$ 150 28,100$ 750$ 28,850$ TOTAL TASKS 160 210 14 90 200 12 450$ 686 118,870$ 450$ 119,320$ 10 75 120 163 8 34 4 32 300$ 446 89,836$ 300$ 90,136$ 1132 208,706$ 750$ 209,456$ Required Tasks Orange Memorial Park Stormwater Capture Project No.: sd1801 Subconsultant: Brown & Caldwell Project Summary Project Lead, Engineering Design, Site Development Engineering, Stormwater Management, Regulatory Support, and Water Capture and Reuse Engineering Design, Open Channel Engineering, Structural Engineering, Electrical Engineering, and Mechanical Engineering Subconsultant proposal is available upon request.DRAFT